Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 2 | 30 | 3 | 2 | 7 | 2 | 2 | 8 | 1 | 3 |
Latest contracts (30)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Jun 8, 2026 | ADA Pathway | JOHN'S AFFORDABLE CONCRETE LLC | $36,523 |
| Apr 2, 2026 | Leveling Concrete 3126 | NORTHWEST CONCRETE LVLNG LLC | $5,615 |
| Jul 25, 2025 | Waitsburg SD Maint 2025 Segraves 5155 | NORTHWEST INSTALLATION ENT INC | $7,698 |
| Aug 6, 2024 | (title withheld) Segraves 5026 | NORTHWEST INSTALLATION ENT INC | $4,482 |
| Jun 20, 2024 | 8� chainlink install 927445 | FENCE-IT CO LLC | $6,440 |
| Feb 22, 2024 | Section 2: 40' of 4' tall chainlink with gate 727571 | FENCE-IT CO LLC | $3,865 |
| Feb 22, 2024 | 214' fence refresh 727574 | FENCE-IT CO LLC | $2,615 |
| Feb 22, 2024 | Section 4.1: (2) sections of chainlink and (2) gates PO 727573 | FENCE-IT CO LLC | $4,899 |
| Feb 22, 2024 | Section 3: 4' chainlink fencing and gates 727572 | FENCE-IT CO LLC | $3,250 |
| Feb 22, 2024 | Section 1: 80' of 5' tall chainlink 727570 | FENCE-IT CO LLC | $4,994 |
| Feb 22, 2024 | Section 4.2 NW field chainlink fencing 727575 | FENCE-IT CO LLC | $2,621 |
| Nov 10, 2023 | Waitsburg SD - Waitsbug High School - Boiler down 56253 | ATLAS BOILER/EQUIPMENT CO INC | $1,963 |
| Jul 27, 2022 | Bathroom Finish 13716 | A-1 PLUMBNG & EMERGENCY ROOTER | $5,100 |
| May 17, 2022 | (title withheld) Mohney 4640 | NORTHWEST INSTALLATION ENT INC | $4,207 |
| Dec 29, 2021 | Water bottle fillers P21438 | TOTAL COMFORT SOLUTIONS LLC | $6,495 |
| Nov 5, 2021 | Waitsburg High School - Boiler#2 oil pump 54354 | ATLAS BOILER/EQUIPMENT CO INC | $2,651 |
| Oct 7, 2021 | Waitsburg Elementary - replace new Honeywell Mod Motor 54174 | ATLAS BOILER/EQUIPMENT CO INC | $2,894 |
| Jun 21, 2021 | Waitsburg High School & Gymnasium Re-Roof None Assigned | S Q I INC | $296,200 |
| Jan 21, 2021 | Waitsburg High School - Boiler not running properly 53708 | ATLAS BOILER/EQUIPMENT CO INC | $1,886 |
| Jan 21, 2021 | Waitsburg School Dist- tune boiler 53627 | ATLAS BOILER/EQUIPMENT CO INC | $2,551 |
| Aug 19, 2020 | Waitsburg Elementry School 20869 | YOUNG'S HEATING & COOLING LLC | $4,353 |
| Mar 26, 2020 | Boiler Service 53095 | ATLAS BOILER/EQUIPMENT CO INC | $783 |
| Feb 5, 2019 | Waitsburg SD - 2017 Bond Projects 17050 | DGR Grant Construction, Inc. | $2,829,000 |
| Mar 26, 2018 | Waitsburg SD - 2017 Bond Projects 17050 | DGR*Grant Construction Inc | $2,829,000 |
| Nov 7, 2017 | (title withheld) Colter 3881 | NORTHWEST INSTALLATION ENT INC | $2,995 |
| Jan 13, 2017 | Waitsburg School Boiler Repair 42080 | ATLAS BOILER/EQUIPMENT CO INC | $1,513 |
| Jun 17, 2016 | 16-02294 Waitsburg SD - E-Rate Wireless & Switching Installation 11158 | EDNETICS INC | $69,449 |
| Nov 13, 2015 | (title withheld) 620262 | NORTHWEST INSTALLATION ENT INC | $2,937 |
| Feb 21, 2014 | 64479 WAITSBURG SCHOOL STOVE 64479 WAITSBURG SCHOOL OVEN | COFFEY REFRIGERATION | — |
| Jun 19, 2012 | Replace Damaged Door 01502202 | OVERHEAD DOOR CO/WALLA WALLA | $4,694 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.