Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 3 | 9 | 6 | 9 | 4 | 7 | 4 | 3 | 7 | 7 |
Latest contracts (57)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Aug 12, 2026 | 2026 Tree Trimming and Vegetation Management Wahkiakum PUD Project #26-1276 | DAVEY TREE SURGERY CO | $125,000 |
| Jun 4, 2026 | Greenwood Reservoir-Sevice call-TS Pump 1 4526156PW | ADVANCED ELECTRICAL TECHNLGIES | — |
| Apr 4, 2026 | Skamokawa Main Lift Station 4526107PW | ADVANCED ELECTRICAL TECHNLGIES | — |
| Feb 5, 2026 | Little River Rd. Lift Station TS 4526047PW | ADVANCED ELECTRICAL TECHNLGIES | — |
| Feb 5, 2026 | Kent's Reservoir 4526046PW | ADVANCED ELECTRICAL TECHNLGIES | — |
| Jan 26, 2026 | Tugboat Lift Station - PLC Addition 4526029 | ADVANCED ELECTRICAL TECHNLGIES | $3,000 |
| Jan 26, 2026 | Westside Water Plant - Autodialer 4526030 | ADVANCED ELECTRICAL TECHNLGIES | $5,450 |
| Dec 18, 2025 | WWTP - Inst. and Programming 4525015PW | ADVANCED ELECTRICAL TECHNLGIES | — |
| Dec 8, 2025 | (title withheld) 0825132 | LAKESIDE INDUSTRIES INC | $8,865 |
| Nov 26, 2025 | Reservoir level T/S 4425305PW | TAURUS POWER AND CONTROLS | — |
| Nov 4, 2025 | Reservoir level T/S 4425305PW | TAURUS POWER AND CONTROLS | — |
| Sep 30, 2025 | Misc. Electricak Upgrades 4425280PW | TAURUS POWER AND CONTROLS | — |
| Mar 5, 2025 | 2025 Tree Trimming and Vegetation Management Wahkiakum PUD Project #25-1183 | DAVEY TREE SURGERY CO | $125,000 |
| Jan 14, 2025 | Wahkiakum PUD Level 2 EV Charging Station Installation 24-1123 | WILD HARE ELECTRIC LLC | $7,846 |
| Oct 15, 2024 | PUGET ISLAND WELL DRILLING AND TESTING 24237.00 | SCHNEIDER EQUIPMENT INC | $287,610 |
| Jul 23, 2024 | Receptacle for portable handwashing stations 21001868 | RAWHIDE ELECTRIC SERVICES LLC | $3,601 |
| Jul 16, 2024 | 2024 Tree Trimming and Vegetation Managemnt Wahkiakum PUD Project# 24-1090 | DAVEY TREE SURGERY CO | $125,000 |
| Jun 9, 2023 | Flagging and Traffic Control INV42300 | NWTCI | — |
| May 24, 2023 | 2023 Tree Trimming and Vegetation Management Project No. 23-1996 | DAVEY TREE SURGERY CO | — |
| Apr 16, 2023 | Arness Janitorial 2023-0001 | ARNESS, JULIE LYNN | $10,800 |
| Mar 28, 2023 | 502 Columbia st na | NIELSON'S MAINTENANCE | $9,000 |
| Nov 10, 2022 | Wahkiakum PUD Asbestos Abatement Public Small Works | 3 KINGS ENVIRONMENTAL INC | $6,800 |
| Oct 31, 2022 | Flagging & Traffic Control INV 41944 | NWTCI | — |
| Aug 4, 2022 | Ditch cut Salmon Creek Road n/a | NASELLE ROCK & ASPHALT CO | $2,060 |
| Apr 29, 2022 | Water Tank Inspections 22-130 | Advanced Diving Services, Inc. | $4,984 |
| Mar 21, 2022 | Power Pole Inspection, Testing and Treating 22-1829 | NATIONAL WOOD TREATING COMPANY | $86,080 |
| Mar 4, 2022 | Arness Janitorial Contract 2022 2022-001 | ARNESS, JULIE LYNN | $10,800 |
| Jun 15, 2021 | Wahkiakum Co. PUD Ditch Cut N/A | NASELLE ROCK & ASPHALT CO | $2,781 |
| May 6, 2021 | Wahkiakum PUD Pole Inspection WK19-002 | PACIFIC POLE INSPECTION LLC | $41,000 |
| Aug 3, 2020 | (title withheld) 2018-3572 | ADVANCED EXCAVATING SPCLTS LLC | $451,989 |
| Jul 30, 2020 | River Street 40347 | NWTCI | — |
| Aug 21, 2019 | Cathlamet Substation | TRANSFORMER TECHNOLOGIES LLC | $7,950 |
| Jul 17, 2019 | Grays River Substation Rebuild | POWER TECHNOLOGY INC | $339,300 |
| Jun 20, 2019 | Tree Trimming MP41-MP45 | NWTCI | — |
| May 23, 2019 | Wahkiakum County PUD Salmon Ck and State Rd Ditchcuts N/A | NASELLE ROCK & ASPHALT CO | $2,340 |
| Sep 20, 2018 | Wahkiakum PUD Door Installation 2018037 | PACIFIC NORTHERN ENVIRO LLC | $13,852 |
| Sep 14, 2018 | Stairs and Handrail | SUPERIOR WELDING AND FABRI LLC | $18,765 |
| Sep 7, 2018 | www system plc upgrades | HAMER ELECTRIC INC | $33,281 |
| Aug 13, 2018 | Utility Install | SAM LONGTAIN CONSTRUCTION | — |
| Jul 30, 2018 | Parking Lot Seal Coating | Olson Asphalt Maintenance LLC | $5,254 |
| Jul 17, 2018 | Wahkiakum PUD Door Installation 2018037 | PACIFIC NORTHERN ENVIRO CORP | $12,874 |
| Jun 8, 2018 | Wahkiakum PUD Door Installation 2018037 | PACIFIC NORTHERN ENVIRO CORP | $12,874 |
| Jan 16, 2018 | Wahkiakum New Phone System 8949 | AMERICA'S PHONE GUYS | $7,000 |
| Jan 8, 2018 | Reception desk remodel Tramblie | QUALITY CABINETS PLUS INC | $17,042 |
| Aug 18, 2017 | PUD OFFICE BUILDING-EXTERIOR/WATER WAREHOUSE-EXTERIOR | Hendrickson Painting Inc | — |
| Aug 7, 2017 | Wahkiakum Tie/Bore | MAGNUM POWER LLC | $14,526 |
| Dec 1, 2016 | Deep River relay station 101 | BURNS CONSTRUCTION INC | $3,554 |
| Oct 20, 2016 | West Deep River Rd Ditchcut n/a | NASELLE ROCK & ASPHALT CO | — |
| Jun 28, 2016 | Wahkiakum PUD | SPEER TAPS INC | $7,102 |
| May 10, 2016 | PUD Warehouse Building | HENDRICKSON PAINTING | $13,719 |
| Sep 7, 2015 | DeepRiver Project DeepRiver | SAM LONGTAIN CONSTRUCTION | $13,590 |
| Jan 29, 2015 | Power to East Malone Creek Road | SAM LONGTAIN CONSTRUCTION | $11,653 |
| Feb 4, 2014 | (title withheld) 14-084 | OVERHEAD DOOR CO OF S W WA | $2,640 |
| Jun 24, 2013 | Ditchcut 2nd St & Una n/a | NASELLE ROCK & ASPHALT CO | $5,035 |
| May 24, 2012 | Wahkiakum Substation WK11-003 | J H KELLY LLC | $858,483 |
| Dec 15, 2011 | Drum Disposal 9311304 | COWLITZ CLEAN SWEEP | — |
| Oct 21, 2011 | Cathlamet Sub Station n/a | SAM LONGTAIN CONSTRUCTION | — |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.