VERA WATER & POWER DISTRICT #15 — public works contracts
79 public works projects and 223 intents to pay prevailing wages name VERA WATER & POWER DISTRICT #15 as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Water/Sewer District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 13 | 12 | 7 | 3 | 22 | 12 | 13 | 4 | 9 | 5 |
Latest contracts (52)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Sep 10, 2026 | Tree Trimming Contract 2025 Tree Trimming 2025 | ASPLUNDH TREE EXPERT LLC | $300,000 |
| Mar 4, 2026 | (title withheld) VERA-004-26 | CASCADE CABLE CONSTRS INC | $13,487 |
| Mar 4, 2026 | 15705 E Broadway VERA-003-26 | CASCADE CABLE CONSTRS INC | $79,219 |
| Feb 10, 2026 | (title withheld) 20111 | CASCADE CABLE CONSTRS INC | $12,410 |
| Feb 10, 2026 | (title withheld) 20112 | CASCADE CABLE CONSTRS INC | $22,453 |
| Nov 17, 2025 | Tree Trimming contract 2024 Tree Trimming 2024 | ASPLUNDH TREE EXPERT LLC | — |
| May 20, 2025 | (title withheld) AVPWR-002-25 | CASCADE CABLE CONSTRS INC | $19,994 |
| May 20, 2025 | (title withheld) VERA-001-25 | CASCADE CABLE CONSTRS INC | $4,935 |
| May 19, 2025 | 1MG Reservoir Recoating Engineer Project NO 124-23 | COATINGS UNLIMITED | $1,253,439 |
| Sep 9, 2024 | Schedule A 4MG Reservoir Recoating Project - | T BAILEY INC | $2,431,007 |
| Dec 14, 2023 | Tree Trimming Contract 2022 Tree Trimming 2022 | ASPLUNDH TREE EXPERT LLC | — |
| Sep 26, 2023 | Open Office 322670 | OPENSQUARE | $10,885 |
| Jun 28, 2023 | Tree Trimming Contract 2023 Tree Trimming 2023 | ASPLUNDH TREE EXPERT LLC | — |
| May 16, 2023 | Vera W&P Office 416821 | OPENSQUARE | $77,221 |
| Nov 15, 2022 | Vera Water & Power Lobby Renovation 1925 | DARDAN ENTERPRISES INC | $649,300 |
| Apr 19, 2022 | 4MG Reservoir Overflow Main 124-11 | ACI NORTHWEST INC | $314,220 |
| Nov 2, 2021 | Vera Crest Dr VERA-003-21 | CASCADE CABLE CONSTRS INC | $29,255 |
| Jul 28, 2021 | 14315 E 35th Ln VERA-002-21 | CASCADE CABLE CONSTRS INC | $14,367 |
| Jun 9, 2021 | Tree Trimming Contract 2021 Tree Trimming 2021 | ASPLUNDH TREE EXPERT LLC | — |
| Mar 24, 2021 | Vera Water & Power Vehicle/Storage Shop Addition 1902 | HALME BUILDERS INC | $773,190 |
| Mar 4, 2021 | Ball Booster Station Replacement Project 124-18 | GENERAL INDUSTRIES INC | $1,424,718 |
| Dec 3, 2020 | (title withheld) VERA-003-20 | CASCADE CABLE CONSTRS INC | $83,940 |
| Aug 27, 2020 | 14323 E 12th VERA-002-20 | CASCADE CABLE CONSTRS INC | $36,469 |
| Jan 27, 2020 | Tree Trimming Contract 2020 Tree Trimming 2020 | ASPLUNDH TREE EXPERT LLC | — |
| Oct 8, 2019 | Bolo's Cable Replacement VERA-005-19 | CASCADE CABLE CONSTRS INC | $15,006 |
| Oct 8, 2019 | 14922 E Belle Terre Ave VERA-006-19 | CASCADE CABLE CONSTRS INC | $21,872 |
| Sep 19, 2019 | Randy Grinal's Cable Replacement VERA-004-19 | CASCADE CABLE CONSTRS INC | $15,438 |
| Aug 1, 2019 | (title withheld) VERA-003-19 | CASCADE CABLE CONSTRS INC | $32,104 |
| Jul 31, 2019 | Belle Terre Ave VERA-002-19 | CASCADE CABLE CONSTRS INC | $25,701 |
| Feb 25, 2019 | Tree Trimming Contract for the Electric Division January 2019 Contract | Asplundh Tree Expert LLC | — |
| Feb 21, 2018 | VALLEYWAY & SULLIVAN SUBSTATION MODIFICATIONS | POWER CITY ELECTRIC INC | $847,777 |
| Feb 20, 2018 | 2018 Tree Trimming Contract | ASPLUNDH TREE EXPERT LLC | — |
| Feb 16, 2018 | SUBSTATION FOUNDATION AND CONDUIT MODIFICATIONS | POWER CITY ELECTRIC INC | $37,769 |
| Feb 1, 2018 | Vera Power System Expansion R2018.06 | PCI RENEWABLES INC | $26,712 |
| Jun 12, 2017 | VERA SUBSTATION | POWER CITY ELECTRIC INC | $259,185 |
| Feb 27, 2017 | 2017 Tree Trimming Contract/Electric Division | ASSOCIATED ARBORIST | — |
| Oct 24, 2016 | Vera Vehicle Maintenance Shop | HALME BUILDERS INC | $539,152 |
| Jun 13, 2016 | Vera Power Community PV 8441 | PCI RENEWABLES INC | $13,885 |
| May 11, 2016 | SUBSTATION 8334/420552 | POWERCOM INC | $5,349 |
| Jan 28, 2016 | 2016 Tree Trimming 2016 Tree Trimming | ASPLUNDH TREE EXPERT CO | — |
| Jan 15, 2016 | Sun Acres Lift Station 124-08-40 | WM WINKLER COMPANY | $811,647 |
| Jan 14, 2016 | VERA WATER & POWER 16TH AVENUE SUBSTATION 15-0002-EN | POWER CITY ELECTRIC INC | $2,734,865 |
| Jan 6, 2016 | Turtle Meter Change Out Project 1 | Sooner Meter Sales & Serv Inc. | $64,000 |
| Sep 30, 2015 | 2015 Tree Trimming Contract 2015 Tree Trimming Contract | ASPLUNDH TREE EXPERT CO | — |
| Jun 23, 2015 | S. Woodlawn Rd. Water Main 124-13-01 | S & L UNDERGROUND INC | $587,129 |
| Mar 4, 2015 | Vera Water & Power Well No. 3 Electrical Upgrade | SHANNON INDUSTRIAL CONTRS INC | $49,785 |
| Jan 31, 2014 | 2014 tree trimming 2014 | AFFORDABLE ARBRIST TREE CR INC | — |
| Jan 29, 2013 | 2013 tree trimming 2013 | AFFORDABLE ARBRIST TREE CR INC | $40,764 |
| Aug 5, 2012 | Well 4 Pump Station Replacement | KIRBY HUNT CONSTRUCTION LTD | $644,061 |
| Jun 29, 2012 | Vera Garage & Office Building Remodel 12032 | ASSOCIATED CONSTRUCTION INC | $525,021 |
| Feb 2, 2012 | 2012 tree trimming 2012 | AFFORDABLE ARBRIST TREE CR INC | $27,520 |
| Oct 17, 2011 | Well 4 Replacement Test/Production Well | HOLT SERVICES INC | $161,310 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.