UNDERWOOD CONSERVATION DIST — public works contracts
18 public works projects and 26 intents to pay prevailing wages name UNDERWOOD CONSERVATION DIST as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Conservation District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2022 | 2023 |
|---|---|---|---|---|---|---|---|---|---|
| 4 | 1 | 2 | 1 | 4 | 1 | 2 | 6 | 4 | 1 |
Latest contracts (18)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Jun 29, 2023 | Slavens Water Line Repair 2023-01 | SIEBERT EXCAVATING LLC | — |
| Nov 14, 2022 | Slavens Western Pond Turtle Pnd Liner 509-493-1936 | NORTHWEST LNG/GEOTXTL PRD INC | $27,704 |
| Sep 29, 2022 | Slavens Western Pond Turtle Habitat Enhancement Project 2202-04 | NORTH CASCADE EXCAVATING LLC | $60,157 |
| Sep 28, 2022 | Trout lake Creek bank stabilization 2022-02 | EXO CONTRACTING LLC | $108,088 |
| Nov 19, 2019 | Little Wind Phase 4 Little Wind Phase 4 | KYSAR AND KOISTINEN INC | — |
| Jul 2, 2019 | Little Wind River 19507 | Columbia Helicopters, Inc. | $65,000 |
| Jun 24, 2019 | 2019 additional work wsid pipeline 1a project 1a2019-03 | M & M EXCAVATING LLC | $20,050 |
| Jun 20, 2019 | WSID Phase 1b Pipeline project 2019-02 | M & M EXCAVATING LLC | $265,737 |
| Jun 20, 2019 | WSID Phase 1b Fish Passage and Fish Screen Project 2019-01 | M & M EXCAVATING LLC | $414,747 |
| Sep 24, 2018 | WFID phase 1a pipeline project | M & M EXCAVATING LLC | $375,110 |
| Mar 6, 2018 | Mill Creek Lakeview Road Catch Basin 2018-03 | SUMMIT EXCAVATION LLC | $9,924 |
| Oct 3, 2017 | Stevens Family Resources Habitat Enhancement 2017 | AQUATIC CONTRACTING LLC | $11,021 |
| Jun 16, 2016 | Mill Creek Fish Passage 2016-02 | JAMES DEAN CONSTRUCTION INC | $476,589 |
| Aug 19, 2015 | Cannavina Creek Fish Passage Cannavina Creek Fish Passage | KYSAR AND KOISTINEN INC | $63,220 |
| Aug 13, 2014 | Little Wind River Community Habitat Restoration Project 2014-06 | AQUATIC CONTRACTING LLC | $55,382 |
| Aug 22, 2013 | Little Wind River Community Habitat Restoration Project 2013-03 | CRESTLINE CONST COMPANY LLC | $56,242 |
| Sep 13, 2012 | Little Wind Comunity Habitat Restoration Project 2012-4 | KYSAR AND KOISTINEN INC | $143,058 |
| Jul 3, 2012 | Indian Crk. - Fish Passage Project 2012-03 | MCNEALY EXCAVATING INC | $199,043 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 19 contractors with the most filings on this agency's projects, prime and subcontractors together.