LAKE CHELAN RECLAMATION DISTRICT — public works contracts
39 public works projects and 69 intents to pay prevailing wages name LAKE CHELAN RECLAMATION DISTRICT as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Diking/Drainage/Irrigation District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 4 | 4 | 3 | 12 | 9 | 5 | 3 | 9 | 1 |
Latest contracts (21)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Oct 20, 2025 | Irrigation Pumping Plants E,G, and H LCR0240161.00 | FARMERS ELECTRIC II LLC | $1,403,636 |
| Jan 21, 2025 | Replace fire system 12125 | KEYHOLE SECURITY INC | $24,008 |
| Jan 15, 2025 | Replace Intrusion System 11425 | KEYHOLE SECURITY INC | $5,380 |
| Feb 28, 2024 | (title withheld) 11-45 LC | PRIME ELECTRIC LLC | $19,485 |
| Aug 9, 2023 | Lift Station No. 2 Upgrades 31-75 | KRCI LLC | $731,740 |
| May 11, 2023 | Zinni Property 01132023 | TRENCHLESS CONST SERVICES LLC | $12,860 |
| Oct 3, 2022 | Water Emergency Generator Improvements | FARMERS ELECTRIC II LLC | $92,651 |
| Sep 21, 2022 | Lakeshore Reservoir Rehabilitation #21-107 | COATINGS UNLIMITED | $78,247 |
| Jul 25, 2022 | Peterson Sewer Crossing 07252022 | TRENCHLESS CONST SERVICES LLC | $12,000 |
| Jun 29, 2022 | Irrigation Pumping Plant Electrical System Upgrades LCR 21.0246 | NORTHEAST ELECTRIC LLC | $1,472,000 |
| May 4, 2021 | Lake Chelan Pumping Plant LCR 20.0122 | BURKE ELECTRIC LLC | $1,372,601 |
| Apr 21, 2021 | Boetzkes Ave Watermain Replacement 21059 | PIPKIN CONSTRUCTION | $345,861 |
| May 14, 2020 | LC PUMPING PLANT ELECTRICAL SYSTEMS UPGRADES | FARMERS ELECTRIC II LLC | $965,005 |
| Apr 10, 2020 | Water Treatment Plant Lighting Retro WATERTXRETRO | Zuluaga Electric | $17,278 |
| Jul 15, 2019 | Swartout Domestic Waterline Extension 2019 | TRENCHLESS CONST SERVICES LLC | $60,140 |
| Mar 27, 2019 | Intake Bank Stabilization LCR 217.091 | OLIN EXCAVATION LLC | $106,036 |
| Mar 4, 2019 | Irrigation Pumping Plant SCADA System Upgrades Phase 2 x | EQUITY BUILDERS LLC | $192,595 |
| Feb 27, 2018 | Irrigation Pumping Plant SCADA System Upgrades | EQUITY BUILDERS LLC | $107,118 |
| Feb 26, 2018 | HVAC Upgrade | M & J HEATING AND COOLING LLC | $17,691 |
| Jan 28, 2017 | LK CH RECL DIST NEW DOORS | DOOR-TECH INC | $6,491 |
| Sep 29, 2012 | 80 Wapato Way, Manson, WA | A & W PAVING INC | $9,016 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.