ILWACO, PORT OF — public works contracts
104 public works projects and 136 intents to pay prevailing wages name ILWACO, PORT OF as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Port District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 |
|---|---|---|---|---|---|---|---|---|---|
| 7 | 6 | 9 | 1 | 27 | 21 | 14 | 10 | 2 | 12 |
Latest contracts (62)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Oct 13, 2025 | Paving xxx | WIRKKALA CONTRACTING INC | $55,939 |
| Feb 25, 2025 | Stormwater Clean Out 7225158 | COWLITZ CLEAN SWEEP | $26,000 |
| Dec 13, 2024 | Port of Ilwaco Bulkhead Resilience Project Bulkhead Project | BERGERSON CONSTRUCTION INC | $3,661,844 |
| Nov 22, 2023 | Ilwaco Office 23-1002 | SABELHAUS WEST INC | $5,430 |
| Oct 17, 2023 | Port of Ilwaco Board Room 210698 | GREAT FLOORS | $8,235 |
| Aug 24, 2023 | POI Storage Yard Fence Replacement Project #23-1001 | BEAR POWER FENCING LLC | $14,288 |
| Aug 17, 2023 | Port of Ilwaco Boat Launch Area Renovation 18-2373D | BEACH TIME LANDSCAPING INC | $13,211 |
| May 17, 2023 | RCO RESTROOM 22-1021-01 | LINDSTROM & SON CONST INC | $106,946 |
| Feb 14, 2023 | Outer Harbor 00213 | C X T INCORPORATED | $81,573 |
| Jan 11, 2023 | Port of Ilwaco - Maintenance Shop Roof 22-0919-01 | DR ROOF INC | $45,960 |
| Sep 26, 2022 | Replace Whse #2 Meter 22-0926-01 | POLAR ELECTRIC LLC | $4,648 |
| May 23, 2022 | Port of Ilwaco & Marina mowing 2022 Mowing | ALLEN PROPERTIES LLC | $4,050 |
| Feb 2, 2022 | (title withheld) 2022 Gardening | TANGLY COTTAGE GARDENING | $9,500 |
| Feb 1, 2022 | Dredge Pipe Towage 21-0810-02 | WCT MARINE & CONSTRUCTION INC | $12,000 |
| Jan 25, 2022 | Dredge Marine Lift at Chinook Marina - Roundtrip 21-0503-01 | BARNHART CRANE AND RIGGING CO | $35,000 |
| Jun 28, 2021 | Building 6 Welder 21-0604-01 | POLAR ELECTRIC LLC | $3,983 |
| Jun 22, 2021 | Repair of Electrical Deficiencies 21-0525-02 | POLAR ELECTRIC LLC | $2,898 |
| May 12, 2021 | Port of Ilwaco Airport & Marina, mowing 2021 Mowing | ALLEN PROPERTIES LLC | $4,200 |
| May 10, 2021 | (title withheld) 21-0507-01 | POLAR ELECTRIC LLC | $2,688 |
| Feb 25, 2021 | (title withheld) 2021 Gardening | TANGLY COTTAGE GARDENING | $8,500 |
| Nov 5, 2020 | Boat Launch Area Chip-Fog-MicroCoat 20-0525-01 | SIERRA SANTA FE CORP | $92,608 |
| Nov 2, 2020 | Boat Ramp Parking Lot & Loop, P Float Parking Stalls & Harbor Way Striping 20-0915-01 | Olson Asphalt Maintenance LLC | $5,621 |
| Oct 23, 2020 | Port of Ilwaco Oil Depot 20-1008-01 | DR ROOF INC | $30,857 |
| Oct 15, 2020 | Boatyard Roof Repair 20-0710-01 | DR ROOF INC | $137,994 |
| Sep 17, 2020 | (title withheld) 2020 Gardening | TANGLY COTTAGE GARDENING | — |
| Sep 1, 2020 | Boatyard Drainage Improvements Nancy Lockett | LINDSTROM & SON CONST INC | $279,849 |
| Aug 3, 2020 | Mowing at port of Ilwaco Airport 360-642-3143 | ALLEN PROPERTIES LLC | — |
| Apr 2, 2020 | Boatyard Building 2020-0303-01 | Servpro of Grays Hrbr & Pac Co | $4,275 |
| Apr 2, 2020 | Boatyard Building 2020-0127-01 | Servpro of Grays Hrbr & Pac Co | $7,283 |
| Jan 29, 2020 | Vessel Deconstruction Building 2020-0123-01 | LARRY HELLIGSO CONSTRUCTION CO | $1,282,674 |
| Nov 15, 2019 | FLAT PANEL LIGHTING 19-0822-01 | FORD ELECTRIC CO INC | $7,688 |
| Dec 17, 2018 | POI dredge and equipment roundtrip haul to and from Chinook 18-1203-01 | Wirkalot Trucking | $3,243 |
| Nov 15, 2018 | PORT OF ILWACO, DREDFE MARINA LIFT - ROUNDTRIP 18-1012-01 | BARNHART CRANE AND RIGGING CO | $28,000 |
| Oct 18, 2018 | Howerton Way Bus Stop Repair 18-0904-01 | NASELLE ROCK & ASPHALT CO | $6,500 |
| Jun 15, 2018 | Dredge Disposal Site Material Relocation 360-6423143 | LINDSTROM & SON CONST INC | — |
| Jun 8, 2018 | Ilwaco Airport Rock Delivery | WIRKKALA CONTRACTING INC | — |
| May 21, 2018 | Parking Lot Seal Coating 18-0423-01 | Olson Asphalt Maintenance LLC | $26,554 |
| May 21, 2018 | Port of Ilwaco Office Building Rehabilitation 18-0228-01 | LARRY HELLIGSO CONSTRUCTION CO | $100,115 |
| Oct 23, 2017 | (title withheld) Project #17-0922-01 | Highway Specialized Transport, LLC | $17,500 |
| Oct 11, 2017 | Port of Ilwaco Bathroom | DR ROOF INC | $4,511 |
| Apr 25, 2017 | Freedom Market Lot Paving Project 17-0414-01 | Olson Asphalt Maintenance LLC | $3,876 |
| Apr 6, 2017 | Boat Ramp Paving 17-0120-01 | NASELLE ROCK & ASPHALT CO | $17,535 |
| Mar 7, 2017 | Of load and set 75k Dredge | BARNHART CRANE AND RIGGING CO | $13,036 |
| Jan 26, 2017 | Port of Ilwaco, Dredge Dispost Site Maintenance, Chinook 17-0118-01 | LINDSTROM & SON CONST INC | $3,380 |
| Sep 29, 2016 | Dredge Material Disposal Site Maintenance 16-0913-01 | CLARKE CONSTRUCTION LLC | $26,676 |
| Aug 8, 2016 | Boatyard support building selective demolition and repair 16-0624-01 | LARRY HELLIGSO CONSTRUCTION CO | $92,947 |
| May 2, 2016 | Chip Seal Parking Lot Maintenance 16-0308-01 | Olson Asphalt Maintenance LLC | $29,772 |
| Apr 13, 2016 | Pavillion Repairs 16-0406-01 | S NEWELL MASONRY & CONST | $4,860 |
| Mar 22, 2016 | HALTON PROPERTY ELECTRICAL IMPROVEMENTS 16-0210-01 | FORD ELECTRIC CO INC | $4,880 |
| Jun 4, 2015 | Halton Property Grading & Leveling 15-0423-01 | JUBILEE CONSTRUCTION LLC | $19,902 |
| May 19, 2015 | Boat Hoist Pile Repair | QUIGG BROS INC | $5,860 |
| Sep 24, 2014 | Weir Installation Weir Installation | UNDERWATER EARTH MOVERS INC | $20,000 |
| Sep 23, 2014 | DREDGE FILL SITE | LINDSTROM & SON CONST INC | $32,578 |
| Apr 8, 2014 | Boat Demo And Cleanup | JUBILEE CONSTRUCTION LLC | $9,174 |
| Jul 15, 2013 | Parking Lot Rock and Drainage 13761 | LINDSTROM & SON CONST INC | — |
| Aug 29, 2012 | Ditchcut Repair-Parking Area/Walkway N/A | NASELLE ROCK & ASPHALT CO | $900 |
| Jul 20, 2012 | 2012 Parking Lot Chip Seal | SIERRA SANTA FE CORP | $168,477 |
| May 15, 2012 | Storage Yard Paving n/a | NASELLE ROCK & ASPHALT CO | $23,468 |
| Dec 21, 2011 | Boatyard Maintenance Building | LARRY HELLIGSO CONSTRUCTION CO | $256,294 |
| Jul 22, 2011 | 2011 Parking Lot Chip Seal | SIERRA SANTA FE CORP | $89,996 |
| Jul 22, 2011 | Port of Ilwaco Parking Lot Chipseal Project | WIRKKALA CONTRACTING INC | $122,736 |
| Jun 23, 2011 | (title withheld) n/a | NASELLE ROCK & ASPHALT CO | $830 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.