Hartstene Pointe Water-Sewer District — public works contracts
106 public works projects and 135 intents to pay prevailing wages name Hartstene Pointe Water-Sewer District as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Water/Sewer District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 13 | 13 | 2 | 12 | 6 | 5 | 10 | 10 | 26 | 10 |
Latest contracts (102)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Sep 16, 2026 | Service-Annual PM Service Annual PM | T M G SERVICES INC | $1,004 |
| Jul 16, 2026 | (title withheld) N/A | AAA Septic Tank Company | $6,646 |
| Jun 30, 2026 | Water reservoirs services 2643 | INTEGRATED UNDERWATER SRVS LLC | $6,424 |
| May 8, 2026 | Hartstene Standpipe Reservoir 3344 | INTEGRATED UNDERWATER SRVS LLC | $4,221 |
| Apr 20, 2026 | HVAC preventative maintenance 1014207944 | BRADLEY AIR COMPANY | — |
| Mar 25, 2026 | Treatment Plant Hauling N/A | AAA Septic Tank Company | $5,455 |
| Mar 12, 2026 | Treatment Plant Hauling, March 24 N/A | AAA Septic Tank Company | $7,819 |
| Feb 17, 2026 | Lift Station Promontory Rd, Feb 15 N/A | AAA Septic Tank Company | $809 |
| Feb 12, 2026 | (title withheld) INV.54675 | T M G SERVICES INC | $15,351 |
| Dec 18, 2025 | Re-Roofing Four Small Roofs | ASCEND ROOFING COMPANY | $14,000 |
| Sep 22, 2025 | 2025 Annual Maintenance 2025 Annual Maint-53960Inv. | T M G SERVICES INC | $3,600 |
| Sep 17, 2025 | (title withheld) N/A | AAA Septic Tank Company | $6,777 |
| Aug 12, 2025 | Aug 11, Treatment Plant Hauling N/A | AAA Septic Tank Company | $5,613 |
| Jul 8, 2025 | July 5th Lift Station Hauling N/A | AAA Septic Tank Company | $1,607 |
| Jun 13, 2025 | Treatment Plant Hauling, June 10 N/A | AAA Septic Tank Company | $6,131 |
| Jun 4, 2025 | CAL-VAL REBUILD CLA-VAL | CIMCO-GC SYSTEMS LLC | $7,176 |
| Apr 18, 2025 | HVAC service 1014207943 | BRADLEY AIR COMPANY | — |
| Jan 30, 2025 | Sewer System Rehabilitation 35020.003.01 | ROGNLINS INC | $15,495,802 |
| Jan 12, 2025 | Bluff Emergency repair Bluff1 | HANSON EXCAVATION LLC | $5,768 |
| Jan 2, 2025 | Cla-Val Rebuild Cla-Val Rebuild | CIMCO-GC SYSTEMS LLC | $11,863 |
| Nov 14, 2024 | Nov 13 Treatment Plant Hauling N/A | AAA Septic Tank Company | $4,580 |
| Nov 4, 2024 | Pointes Drive Sewer PD1 | HANSON EXCAVATION LLC | $6,686 |
| Nov 4, 2024 | 451 North Beach NB1 | HANSON EXCAVATION LLC | — |
| Sep 11, 2024 | 2024 Annual Maintenance Inv.52301 | T M G SERVICES INC | $3,636 |
| Aug 30, 2024 | Treatment Plant Hauling N/A | AAA Septic Tank Company | $4,940 |
| Jun 28, 2024 | Treatment Plant Hauling N/A | AAA Septic Tank Company | $4,969 |
| Jun 6, 2024 | Treatment Plant Hauling N/A | AAA Septic Tank Company | $4,449 |
| May 20, 2024 | 310 312 E Pointes Waterline repair 310312 | HANSON EXCAVATION LLC | — |
| May 14, 2024 | Warranty work on ductless heat pump 1014205959 | BRADLEY AIR COMPANY | $2,058 |
| May 8, 2024 | Treatment Plant Hauling 042224 | AAA Septic Tank Company | $5,543 |
| Dec 4, 2023 | Treatment Plant Hauling 001 | AAA Septic Tank Company | $5,483 |
| Aug 30, 2023 | Treatment Plant Hauling 001 | AAA Septic Tank Company | $5,694 |
| Aug 28, 2023 | Service Annual Maint service annual maintenance | T M G SERVICES INC | $3,425 |
| Jul 15, 2023 | Wiring for replaced influent gate motors. 806732 | BRIGHT KNIGHTS LLC | — |
| Jun 30, 2023 | (title withheld) 001 | AAA Septic Tank Company | $5,787 |
| Jun 27, 2023 | Replace effluent pump disconnects 806711 | BRIGHT KNIGHTS LLC | — |
| Apr 29, 2023 | HARSTINE POINTE SEWER 69192046 | ROBISON PLUMBING SERVICE INC | $9,157 |
| Apr 17, 2023 | Chesapeake Treatment Plant Hauling 001 | AAA Septic Tank Company | $4,797 |
| Mar 27, 2023 | (title withheld) 2023-317 | HANSON EXCAVATION LLC | — |
| Jan 30, 2023 | Harstine Pointe Sewer District 63497335 | ROBISON PLUMBING SERVICE INC | $16,343 |
| Nov 29, 2022 | (title withheld) 002 | HANSON EXCAVATION LLC | — |
| Sep 9, 2022 | (title withheld) 001 | AAA Septic Tank Company | $4,887 |
| Aug 3, 2022 | 329 Pointes Drive East Sewer lateral repair 329 | HANSON EXCAVATION LLC | — |
| Jul 22, 2022 | (title withheld) 001 | AAA Septic Tank Company | $5,985 |
| Jun 8, 2022 | Install Ductless Heat Pump 79581187 | BRADLEY AIR COMPANY | $9,070 |
| Oct 27, 2021 | (title withheld) Verbal | NICHOLSON DRILLING INC | $3,320 |
| Sep 2, 2021 | Repair service entrance conduit to 562 Pointes DR West. 709344 | BRIGHT KNIGHTS LLC | — |
| Jul 14, 2021 | Add time clock for plant generator 709342 | BRIGHT KNIGHTS LLC | — |
| Jun 1, 2021 | Septic Pumping 001 | AAA Septic Tank Company | $5,945 |
| Jan 7, 2021 | Outfall Repair | ENVIRO-TECH DIVING INC | $26,756 |
| Dec 18, 2020 | Hartstene Point Inv 66116509 | NORTHWEST CASCADE INC | $2,937 |
| Dec 18, 2020 | Hartstene Point Inv 66116511 | NORTHWEST CASCADE INC | $2,626 |
| Dec 18, 2020 | Hartstene Point Inv 66116508 | NORTHWEST CASCADE INC | $3,494 |
| Nov 17, 2020 | Nantucket Lift Station 1900244413 | GRUNDFOS CBS INC | $8,635 |
| Jul 27, 2020 | Hartstene Point Inv 66106902 | NORTHWEST CASCADE INC | $1,758 |
| Jul 27, 2020 | Hartstene Point Inv 66106900 | NORTHWEST CASCADE INC | $3,494 |
| Jul 27, 2020 | Harstene Point Inv 66106904 | NORTHWEST CASCADE INC | $3,755 |
| Jul 16, 2020 | Hartstene Point Inv 66098000 | NORTHWEST CASCADE INC | $3,526 |
| Jul 16, 2020 | Hartstene Point Inv 66098001 | NORTHWEST CASCADE INC | $3,217 |
| Sep 27, 2019 | (title withheld) Hartstene Pointe | NORTHWEST CASCADE INC | $6,879 |
| Aug 21, 2019 | Harstene Pointe Sewer District Harstene Pointe Sewer District | NORTHWEST CASCADE INC | $6,734 |
| Dec 18, 2018 | (title withheld) HPWSD Well 4 Generator | SARE ELECTRIC INC | $20,506 |
| Nov 19, 2018 | Hartstene Pointe Water Dist Pumping | NORTHWEST CASCADE INC | $6,349 |
| Nov 14, 2018 | Flygt Pump troubleshoot | PACO PUMPS | $2,016 |
| Nov 12, 2018 | Groundwater Replacement Well 4 | AM NW Const Partners LLC | $87,142 |
| Sep 17, 2018 | Maintenance on Chlorine Gas System | T M G SERVICES INC | $2,096 |
| Sep 13, 2018 | Hartstene Pointe Pumping 66031982 | NORTHWEST CASCADE INC | $7,834 |
| Jul 11, 2018 | Well Treatment Building Roof Replacement | BLACK DIAMOND ROOFING INC | $6,435 |
| May 10, 2018 | Well #2 Re-Hab | TACOMA PUMP & DRILLING CO. INC | $28,047 |
| May 8, 2018 | Electrical Installation for Reservoir Mixer 8280 | SARE ELECTRIC INC | $3,798 |
| Dec 20, 2017 | Reservoir Cleaning & Inspection | H20 SOLUTIONS LLC | $2,116 |
| Dec 19, 2017 | 2017 Preventative Maintenance WWT11-1-17 | PACO PUMPS | $4,350 |
| Nov 10, 2017 | Hartstene Point Sewer Dist Pumping | NORTHWEST CASCADE INC | $6,184 |
| Sep 8, 2017 | Bio Solids Haul Off WWTF | NORTHWEST CASCADE INC | $5,566 |
| Jul 27, 2017 | PM Service | PACO PUMPS | $3,095 |
| Apr 26, 2017 | In-Plant Lift Station Pump ABS AF22-4 EX3HP WW-32816 | PACO PUMPS | $5,405 |
| Mar 24, 2017 | Maintenance 1 | ZEPHYR'S INC | $3,906 |
| Mar 14, 2017 | In Plant Effluent Pump EFFPUMP2016 | PACO PUMPS | $12,139 |
| Feb 23, 2017 | Wastewater Spill Cleanup 170483-CON; 170483-WTR | SERVICEMASTER OF TACOMA | — |
| Jan 15, 2017 | 111 liberty sewer line replacement N/a | RAPTOR EXCAVATING/CONTRNG LLC | $5,600 |
| Sep 29, 2016 | Well 1R drilling and testing | TACOMA PUMP & DRILLING CO. INC | $73,324 |
| Sep 19, 2016 | Water Treatment Plant Improvments 2016.WTP | 2KG CONTRACTORS INC | $912,821 |
| Sep 15, 2016 | Hartstene Point Water and Sewer | NORTHWEST CASCADE INC | $9,222 |
| Sep 7, 2016 | PRESSURE REDUCING VALVE REPLACEMENT | PAPE & SONS CONSTRUCTION, INC | $21,700 |
| Aug 23, 2016 | Hartstene Pointe Sewer District Bio Solids Removal | NORTHWEST CASCADE INC | $4,980 |
| Jun 24, 2016 | IN PLANT EFFLUENT PUMP WWT 0531416 | PACO PUMPS | $4,338 |
| Jun 17, 2016 | Lift Station 8 Pump 2 Replacement WWT42116 | PACO PUMPS | $10,958 |
| Jun 7, 2016 | (title withheld) 9740 | EVERSON ASPHALT PAVING INC | $5,207 |
| Jan 21, 2016 | HARTSTENE POINTE SEWER DIST | NORTHWEST CASCADE INC | $4,796 |
| Nov 30, 2015 | HPWSD Well #1 Pump Replacement 10-27-15 | BISON WELL DRILLING/SEPTIC LLC | $5,298 |
| Oct 14, 2015 | 329 E Pointes Dr. East Leak Repair Restoration | EVERSON ASPHALT PAVING INC | $4,100 |
| Oct 7, 2015 | WAS Pump Station Improvements | GARY HARPER CONSTRUCTION INC | $69,114 |
| Sep 8, 2015 | Harstene Pointe Water & Sewer Repair P.O. HPWSD9815 | NORTHWEST CASCADE INC | $5,000 |
| Aug 19, 2015 | HARTSTENE PT SEWER DIST | NORTHWEST CASCADE INC | $2,107 |
| Aug 19, 2015 | HARTSTENE PT SEWER | NORTHWEST CASCADE INC | $601 |
| Apr 20, 2015 | HARTSTENE POINTE SEWER DIST BIOSOLIDS WWTB-01132015 | NORTHWEST CASCADE INC | $20,000 |
| Mar 21, 2014 | Well # 1 rehabilitation | TACOMA PUMP & DRILLING CO. INC | $19,346 |
| Nov 26, 2013 | WWTP Headworks Screen Replacement | STAN PALMER CONST INC | $149,947 |
| Sep 17, 2012 | Pump Station Improvements, Schedule B Water Service Meter Installations 2011.BP.B | NORTHERN CON-AGG LLP | $301,032 |
| Jul 2, 2012 | Wastewater Treatment Plant Outfall Improvements | BALLARD DIVING & SALVAGE | — |
| Jun 11, 2012 | Waste water treatment plant entry gate replacement 360 427 2413 | Paul LaDue General Contracting | $2,105 |
| Jan 5, 2012 | Reservoir Pump Station Improvements 2011.BP.A | CLACKAMAS CONSTRUCTION INC | $174,379 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.