FREEMAN SCHOOL DISTRICT #358 — public works contracts
284 public works projects and 385 intents to pay prevailing wages name FREEMAN SCHOOL DISTRICT #358 as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: School District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 4 | 7 | 17 | 16 | 10 | 24 | 76 | 66 | 8 | 9 |
Latest contracts (200)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Sep 8, 2026 | (title withheld) Everett Combs | SME SOLUTIONS LLC | — |
| Aug 10, 2026 | (title withheld) Everett | SME SOLUTIONS LLC | — |
| May 20, 2026 | (title withheld) 7000252608 | Ednetics Inc | $179,194 |
| Apr 28, 2026 | Operator With Equipment Attach na | IDAHO FENCE COMPANY | $39,900 |
| Mar 25, 2026 | 26-11229 Freeman SD Switch Refresh 7000252602 | Ednetics Inc | $48,596 |
| Mar 25, 2026 | Crack Fill Tennis Courts 6020252601 | ARROW CONCRETE & ASPH SPC LLC | $9,909 |
| Mar 23, 2026 | 26-11223 Freeman SD Data Center Refresh 7000252602 | Ednetics Inc | $136,868 |
| Feb 7, 2026 | back up pump seal 4526-069 | CONTROL SOLUTIONS NW INC | $2,415 |
| Feb 7, 2026 | Heat Exchanger Boiler #1 4526-018 | CONTROL SOLUTIONS NW INC | $37,545 |
| Nov 19, 2025 | Shut down cooling towers 4525-947 | CONTROL SOLUTIONS NW INC | $329 |
| Nov 10, 2025 | Freeman Elementary School DW Repair 8986933 | HOBART | — |
| Oct 24, 2025 | RTU -1 Too cold 4525-848 | CONTROL SOLUTIONS NW INC | $703 |
| Oct 23, 2025 | Stand Alone Cooler in Kitchen 4525-769 | CONTROL SOLUTIONS NW INC | $1,382 |
| Sep 26, 2025 | leaking on unit Freeman High School | HOBART | $993 |
| Sep 25, 2025 | unit leaking Freeman High School | HOBART | $787 |
| Mar 5, 2025 | Maintenance Svcs, Spot Calls 4424-016 | CONTROL SOLUTIONS NW INC | $60,000 |
| Feb 6, 2025 | unit making loud screeching noise Freeman School District | HOBART | $658 |
| Dec 31, 2024 | HS HP-23 Shutting Down 4524-1167 | CONTROL SOLUTIONS NW INC | $569 |
| Dec 31, 2024 | HS Capacitor Install 4524-1154 | CONTROL SOLUTIONS NW INC | $330 |
| Dec 26, 2024 | Domestic HW & Softener Fittings Leaking 4524-1160 | CONTROL SOLUTIONS NW INC | $522 |
| Dec 26, 2024 | Bus Garage Heater Not Working 4524-1179 | CONTROL SOLUTIONS NW INC | $697 |
| Dec 24, 2024 | HP-26 in Fault/Not Heating 4524-1148 | CONTROL SOLUTIONS NW INC | $1,843 |
| Dec 23, 2024 | Sports Heater Issues 4524-1133 | CONTROL SOLUTIONS NW INC | $303 |
| Dec 16, 2024 | HS Kitchen Refrigerator Temps 4524-1098 | CONTROL SOLUTIONS NW INC | $645 |
| Dec 12, 2024 | HS H&V-1 Not Heating 4524-1088 | CONTROL SOLUTIONS NW INC | $3,545 |
| Dec 12, 2024 | HS HP-27 Fan/Heating 4524-1090 | CONTROL SOLUTIONS NW INC | $339 |
| Dec 11, 2024 | Middle School DHW Alarm 4524-824 | CONTROL SOLUTIONS NW INC | $3,071 |
| Nov 26, 2024 | Elementary Fire Riser Room New Heater 4524-878 | CONTROL SOLUTIONS NW INC | $4,172 |
| Nov 19, 2024 | Boilers Above Kitchen Leaking 4524-1045 | CONTROL SOLUTIONS NW INC | $2,019 |
| Nov 6, 2024 | Cooling Tower Winterization 4524-1047 | CONTROL SOLUTIONS NW INC | $708 |
| Oct 21, 2024 | High School Training Room Ice Machine Leaking 4524-858 | CONTROL SOLUTIONS NW INC | $885 |
| Oct 15, 2024 | MS Portable Not Cooling 4524-888 | CONTROL SOLUTIONS NW INC | $610 |
| Sep 13, 2024 | Elementary HP Locked out on fan status 4524-820 | CONTROL SOLUTIONS NW INC | $303 |
| Sep 13, 2024 | HS Flow Switch Replacement 4524-786 | CONTROL SOLUTIONS NW INC | $812 |
| Sep 10, 2024 | Cooling Tower 4524-741 | CONTROL SOLUTIONS NW INC | $762 |
| Sep 5, 2024 | leak from bottom of CL44E WO 8390695 | HOBART | $659 |
| Aug 21, 2024 | Maintenance Shop Heater Replacement 4524-560 | CONTROL SOLUTIONS NW INC | $5,535 |
| Jul 30, 2024 | High School Glycol Leak 4524-555 | CONTROL SOLUTIONS NW INC | $343 |
| Jul 30, 2024 | HS Cooling Tower Fault 4524-571 | CONTROL SOLUTIONS NW INC | $532 |
| Jul 30, 2024 | Hot Water Heater Repair 4524-559 | CONTROL SOLUTIONS NW INC | $9,405 |
| Jul 29, 2024 | Walk IN Freezer Alarm/Issues 4524-547 | CONTROL SOLUTIONS NW INC | $1,894 |
| Jul 26, 2024 | HP-22 Blower Motor Replacement 4524-516 | CONTROL SOLUTIONS NW INC | $1,972 |
| Jul 23, 2024 | Booster STN Pump Replct 4524-459 | CONTROL SOLUTIONS NW INC | $9,563 |
| Jun 19, 2024 | Elementary Boiler Loop 4524-449 | CONTROL SOLUTIONS NW INC | $951 |
| Jun 19, 2024 | High School Lock Out Flame 4524-466 | CONTROL SOLUTIONS NW INC | $627 |
| Jun 13, 2024 | HS HP-33 Not Cooling 4524-444 | CONTROL SOLUTIONS NW INC | $465 |
| Jun 12, 2024 | Freezer in Alarm 4524-490 | CONTROL SOLUTIONS NW INC | $1,378 |
| Jun 12, 2024 | Elementary Boiler leaking 4524-440 | CONTROL SOLUTIONS NW INC | $789 |
| Jun 11, 2024 | (title withheld) 4524-393 | CONTROL SOLUTIONS NW INC | $933 |
| Jun 11, 2024 | Transpo Co-Op Failed Bearing 4524-389 | CONTROL SOLUTIONS NW INC | $660 |
| Jun 10, 2024 | HS Chem Closet/Tower Fan parts 4524-327 | CONTROL SOLUTIONS NW INC | $1,517 |
| Jun 10, 2024 | Cooling Tower Fan Stuck 4524-333 | CONTROL SOLUTIONS NW INC | $432 |
| Jun 7, 2024 | Elementary Boiler Drain Leak 4524-287 | CONTROL SOLUTIONS NW INC | $1,410 |
| Jun 7, 2024 | Cooling Towers Start UP 4524-318 | CONTROL SOLUTIONS NW INC | $627 |
| Jun 4, 2024 | Concession Stand Valves 4524-148 | CONTROL SOLUTIONS NW INC | $915 |
| Jun 4, 2024 | Shop Heater Not Working 4524-146 | CONTROL SOLUTIONS NW INC | $465 |
| May 30, 2024 | Elementary Kichen Boilers Overflowing 4524-109 | CONTROL SOLUTIONS NW INC | $2,467 |
| May 22, 2024 | Elementary HRU-2 Not Heating 4524-081 | CONTROL SOLUTIONS NW INC | $1,669 |
| May 22, 2024 | HS Cafeteria RTU Issues 4524-080 | CONTROL SOLUTIONS NW INC | $627 |
| May 8, 2024 | H.S. WH-2 Lock Out on DHW 4524-067 | CONTROL SOLUTIONS NW INC | $424 |
| May 8, 2024 | HS HRU-2 Not Working 4524-040 | CONTROL SOLUTIONS NW INC | $2,606 |
| May 8, 2024 | Elementary Emerg. Heat Mode 4524-065 | CONTROL SOLUTIONS NW INC | $1,585 |
| Apr 24, 2024 | HS-HRU-1 Not Working 4524-039 | CONTROL SOLUTIONS NW INC | $583 |
| Apr 23, 2024 | H.S. HRU-1 Leak 4523-1218 | CONTROL SOLUTIONS NW INC | $2,226 |
| Apr 9, 2024 | Elementary HP-35 No Heat 4524-029 | CONTROL SOLUTIONS NW INC | $586 |
| Apr 9, 2024 | Troubleshoot HS RTU 4524-021 | CONTROL SOLUTIONS NW INC | $627 |
| Apr 9, 2024 | HRU-3 Troubleshooting 4524-028 | CONTROL SOLUTIONS NW INC | $303 |
| Apr 4, 2024 | Trouble Shooting Shop Heater 4524-003 | CONTROL SOLUTIONS NW INC | $586 |
| Mar 28, 2024 | Shop Heater Issues 4524-006 | CONTROL SOLUTIONS NW INC | $586 |
| Mar 22, 2024 | HS Training Rm Leak 4523-1248 | CONTROL SOLUTIONS NW INC | $1,427 |
| Mar 21, 2024 | HS HP-41 Issues 4523-1205 | CONTROL SOLUTIONS NW INC | $465 |
| Mar 20, 2024 | Compressor/contactor installs 4524-102 | CONTROL SOLUTIONS NW INC | $8,379 |
| Mar 14, 2024 | Elementary Freezer Alarm 4523-1187 | CONTROL SOLUTIONS NW INC | $708 |
| Mar 13, 2024 | Shop Heater 4523-1185 | CONTROL SOLUTIONS NW INC | $1,473 |
| Mar 6, 2024 | HRU-3 In Alarm 4523-1184 | CONTROL SOLUTIONS NW INC | $1,577 |
| Mar 1, 2024 | BOILER SVCS ALL SCHOOLS 4523-1172 | CONTROL SOLUTIONS NW INC | $15,801 |
| Feb 22, 2024 | HS CUH-2 Power loss 4523-1136 | CONTROL SOLUTIONS NW INC | $2,709 |
| Feb 16, 2024 | (title withheld) 4523-1136 | CONTROL SOLUTIONS NW INC | $627 |
| Feb 14, 2024 | Blower Wheel Loud 4523-996 | CONTROL SOLUTIONS NW INC | $1,197 |
| Jan 18, 2024 | HS. Winterize Chiller 4523-1046 | CONTROL SOLUTIONS NW INC | $465 |
| Jan 18, 2024 | HS. Heating Issues 4523-1052 | CONTROL SOLUTIONS NW INC | $465 |
| Jan 18, 2024 | Winterize Chiller 4523-1045 | CONTROL SOLUTIONS NW INC | $384 |
| Jan 18, 2024 | Batting Cage Heater issues 4523-1053 | CONTROL SOLUTIONS NW INC | $538 |
| Nov 30, 2023 | RED GYM GLYCOL LEAK 4523-852 | CONTROL SOLUTIONS NW INC | $955 |
| Oct 31, 2023 | Freeman High School Red Gym Crawl Space AIA A101 - 2017 | LYDIG CONSTRUCTION INC | $128,500 |
| Oct 20, 2023 | FHS/FES Sound System 7002200014 | AVIDEX INDUSTRIES LLC | $20,283 |
| Oct 12, 2023 | Flow Switch Replacement 4523-704 | CONTROL SOLUTIONS NW INC | $677 |
| Oct 12, 2023 | (title withheld) 4523-798 | CONTROL SOLUTIONS NW INC | $538 |
| Oct 12, 2023 | HS Water Press. Relief Replacement 4523-718 | CONTROL SOLUTIONS NW INC | $1,064 |
| Oct 12, 2023 | High School Heat Pump 5 Faults 4523-797 | CONTROL SOLUTIONS NW INC | $376 |
| Oct 10, 2023 | Freezer Compressor Sealing 4523-522 | CONTROL SOLUTIONS NW INC | $1,737 |
| Oct 10, 2023 | HP-24 Not Cooling 4523-480 | CONTROL SOLUTIONS NW INC | $2,646 |
| Oct 10, 2023 | Ice Machine Leak-Laundry Rm 4523-646 | CONTROL SOLUTIONS NW INC | $546 |
| Oct 2, 2023 | (title withheld) Everett | SME SOLUTIONS LLC | — |
| Sep 6, 2023 | Emergency Shut Off Valve 4523-651 | CONTROL SOLUTIONS NW INC | $745 |
| Sep 6, 2023 | HS Showers Won't Turn off 4523-652 | CONTROL SOLUTIONS NW INC | $823 |
| Sep 6, 2023 | STUCK VALVE 4523-676 | CONTROL SOLUTIONS NW INC | $657 |
| Aug 31, 2023 | 23-00565 Freeman SD Freeman HS Ticket Booth IPVS T&M | Ednetics Inc | — |
| Aug 11, 2023 | Installation of Scroll Compressor 4523-556 | CONTROL SOLUTIONS NW INC | $1,674 |
| Aug 10, 2023 | Pressure Light/Pump 4523-521 | CONTROL SOLUTIONS NW INC | $719 |
| Aug 4, 2023 | Noisy Motor 4523-519 | CONTROL SOLUTIONS NW INC | $495 |
| Jul 28, 2023 | HP-43 Leak 4523-494 | CONTROL SOLUTIONS NW INC | $332 |
| Jul 27, 2023 | Replacement of Relief Valve 4523-467 | CONTROL SOLUTIONS NW INC | $738 |
| Jul 26, 2023 | Water Line Cracked in HS 4523-455 | CONTROL SOLUTIONS NW INC | $373 |
| Jul 26, 2023 | HS Cooling Tower Alarm 4523-465 | CONTROL SOLUTIONS NW INC | $2,313 |
| Jul 20, 2023 | Hydraulic Door Closer Replacement 4523-445 | CONTROL SOLUTIONS NW INC | $799 |
| Jul 3, 2023 | Mini Split Leak 4523-414 | CONTROL SOLUTIONS NW INC | $973 |
| Jun 19, 2023 | Pre-School Not Cooling 4523-387 | CONTROL SOLUTIONS NW INC | $1,322 |
| Jun 19, 2023 | (title withheld) 4523-399 | CONTROL SOLUTIONS NW INC | $401 |
| Jun 14, 2023 | (title withheld) 4523-384 | CONTROL SOLUTIONS NW INC | $515 |
| Jun 13, 2023 | Cooling Towers Start Up 4523-354 | CONTROL SOLUTIONS NW INC | $597 |
| Jun 13, 2023 | Elem. Kitchen No Heat/HS DHW Tank 4523-345 | CONTROL SOLUTIONS NW INC | $988 |
| Jun 9, 2023 | Elementary VFD Replacement 4523-218 | CONTROL SOLUTIONS NW INC | $6,544 |
| Jun 5, 2023 | Freeman High School Tennis Courts 2023 Tennis Courts | ARROW CONCRETE & ASPH SPC LLC | $7,551 |
| May 24, 2023 | Pump House Heater Not Working 4523-073 | CONTROL SOLUTIONS NW INC | $1,305 |
| May 17, 2023 | DOMESTIC WATER BOILER NOT FIRING 4523-079 | CONTROL SOLUTIONS NW INC | $1,899 |
| May 17, 2023 | High School HRC 4523-085 | CONTROL SOLUTIONS NW INC | $168 |
| May 17, 2023 | HS HOT WATER PUMP REPLC'T 4523-201 | CONTROL SOLUTIONS NW INC | $2,648 |
| May 17, 2023 | High School Heat Pump Not Heating 4523-112 | CONTROL SOLUTIONS NW INC | $4,273 |
| May 17, 2023 | ELEMENTARY HP 36 4523-207 | CONTROL SOLUTIONS NW INC | $1,753 |
| May 17, 2023 | WATER SHUT OFF VALVES-FIELD CONSCESSIONS BLDG 4523-216 | CONTROL SOLUTIONS NW INC | $1,908 |
| May 16, 2023 | HS Domestic Water Line Replct 4523-308 | CONTROL SOLUTIONS NW INC | $1,132 |
| May 16, 2023 | PORTABLE NOT HEATING 4523-173 | CONTROL SOLUTIONS NW INC | $365 |
| May 16, 2023 | (title withheld) 4523-330 | CONTROL SOLUTIONS NW INC | $686 |
| May 16, 2023 | HS RTU-1 NO HEAT 4523-111 | CONTROL SOLUTIONS NW INC | $411 |
| May 16, 2023 | Bus Garage Replace Belt, Pulley, Sheave 15001 S. Jackson, Rockford, WA 99030 | CONTROL SOLUTIONS NW INC | $1,016 |
| May 16, 2023 | HS Milk Cooler Leaking 4523-113 | CONTROL SOLUTIONS NW INC | $243 |
| May 8, 2023 | PRESCHOOL HEAT NOT WORKING 4523-339 | CONTROL SOLUTIONS NW INC | $648 |
| Apr 22, 2023 | Kitchen Freezer Temps Rising 4523-241 | CONTROL SOLUTIONS NW INC | $573 |
| Mar 31, 2023 | Freeman SD Stadium Upgrades 231100 | GARCO CONSTRUCTION INC | $2,702,500 |
| Mar 30, 2023 | Kitchen equipment repair/installs 2023 | HOBART | — |
| Mar 17, 2023 | (title withheld) Everett Combs | SME SOLUTIONS LLC | — |
| Mar 7, 2023 | 23-00185 Freeman SD District IPVS T&M T&M | Ednetics Inc | — |
| Mar 2, 2023 | MULTI-PURPOSE ROOM COLD 4523-181 | CONTROL SOLUTIONS NW INC | $492 |
| Feb 16, 2023 | Freeman SD - Playground Installation 1002200017 | NORTHWEST PLAYGROUND EQUIP INC | $6,512 |
| Jan 17, 2023 | HEAT PUMP FAN ISSUES 4522-930 | CONTROL SOLUTIONS NW INC | $3,397 |
| Jan 13, 2023 | 23-09983 Freeman SD District IPVS Replacements T&M | Ednetics Inc | — |
| Nov 16, 2022 | HS KITCHEN EVAP REPLCT 4522-884 | CONTROL SOLUTIONS NW INC | $5,513 |
| Nov 9, 2022 | HP 21 & 23 MOTOR REPLC'T 4522-822 | CONTROL SOLUTIONS NW INC | $8,620 |
| Nov 7, 2022 | 22-09851 Freeman SD Bus Garage WiFi 5022200016 | Ednetics Inc | $5,640 |
| Oct 4, 2022 | 2022 Freeman High School Tennis Courts 2022 Freeman High School Tennis Courts | ARROW CONCRETE & ASPH SPC INC | $3,187 |
| Aug 12, 2022 | HS WELDING BOOTH EXHAUST 4522-426 | CONTROL SOLUTIONS NW INC | $4,330 |
| Aug 4, 2022 | 22-09581 Freeman SD PROJECT ID E-rate 2022: switches & wireless upgrades - FRN 2299056513 - SPI 7002100020 | Ednetics Inc | $49,515 |
| Aug 2, 2022 | (title withheld) T&M | Ednetics Inc | — |
| Jul 13, 2022 | Freeman Well Pump Replacement 2022-1 | H2O WELL SERVICE INC | — |
| Jun 9, 2022 | (title withheld) 18293896 | WAYNE DALTON SALES & SERVICE | — |
| May 3, 2022 | 22-09345 Freeman SD Outdoor Public Wi-Fi 7002100017 | Ednetics Inc | $6,522 |
| Feb 16, 2022 | Freeman Middle School HVAC Upgrade 2022-1 | TRM SERVICES INC | $1,719,000 |
| Dec 7, 2021 | 21-07986 Freeman SD Multi-site IPVS T&M T&M | Ednetics Inc | — |
| Oct 29, 2021 | 21-07898 Freeman SD Freeman HS Data Cable T&M T&M | Ednetics Inc | — |
| Sep 13, 2021 | (title withheld) Not Yet | Triumph Electric LLC | $120,000 |
| Aug 26, 2021 | 21-07727 Freeman SD Maintenance Bldg IDS T&M T&M | Ednetics Inc | — |
| Jul 2, 2021 | Replacement Slide 05102021KAW01 | NORTHWEST PLAYGROUND EQUIP INC | $7,137 |
| Jun 18, 2021 | (title withheld) Lally 4493 | NORTHWEST INSTALLATION ENT INC | $14,711 |
| Jun 1, 2021 | 21-07410 Freeman SD Freeman MS IPVS T&M T&M | Ednetics Inc | — |
| Mar 15, 2021 | 21-07156 Freeman SD Football Storage IDS T&M T&M | Ednetics Inc | — |
| Feb 23, 2021 | Replace Ice Machine 4521-134 | CONTROL SOLUTIONS NW INC | $3,471 |
| Nov 20, 2020 | 20-06720 Freeman SD Freeman MS ACS T&M T&M | Ednetics Inc | — |
| Oct 23, 2020 | BOILER CONTROLS 4520-730 | CONTROL SOLUTIONS NW INC | $3,375 |
| Oct 12, 2020 | 20-06636 Freeman SD Freeman HS Choir Room Extron T&M T&M | Ednetics Inc | — |
| Aug 12, 2020 | Freeman Middle School Boiler Replacement 2020-3356 | MCCLINTOCK & TURK INC | $144,500 |
| Jun 19, 2020 | Freeman High School Tennis Courts N/A | ARROW CONCRETE & ASPH SPC INC | $1,892 |
| May 28, 2020 | (title withheld) T&M | Ednetics Inc | — |
| May 4, 2020 | (title withheld) T&M | Ednetics Inc | — |
| Apr 2, 2020 | Freeman SD Fiber Verbal | SYSTEM TECH WASHINGTON INC | — |
| Mar 4, 2020 | 20-06086 Freeman SD Fiber Testing customer to pay with credit card | Ednetics Inc | $1,925 |
| Feb 28, 2020 | FREEZER INSTALL 4519-1049 | CONTROL SOLUTIONS NW INC | $17,960 |
| Jan 30, 2020 | 20-06052 Freeman SD PTC 360 Camera T&M T&M | Ednetics Inc | — |
| Dec 17, 2019 | 19-05706 Freeman SD Freeman ES DMP System T&M T&M | Ednetics Inc | — |
| Dec 11, 2019 | High School Heat Pump Issues 4519-877 | CONTROL SOLUTIONS NW INC | $6,070 |
| Nov 8, 2019 | 19-05617 Freeman SD Portables DMP Swap T&M | Ednetics Inc | — |
| Nov 5, 2019 | 19-05603 Freeman SD Freeman MS Extron Move T&M | Ednetics Inc | — |
| Nov 1, 2019 | (title withheld) T&M | Ednetics Inc | — |
| Oct 21, 2019 | (title withheld) T&M | Ednetics Inc | — |
| Sep 26, 2019 | 19-05245 Freeman SD Freeman HS Classroom AV 7001801013, 7001801024 | Ednetics Inc | $91,701 |
| Sep 24, 2019 | Hallway Lighting Retrofit | G E M ELECTRIC NW INC | $4,500 |
| Sep 17, 2019 | 19-05246 Freeman SD Server Systems 7001801014 | Ednetics Inc | $51,364 |
| Aug 19, 2019 | 19-05406 Freeman SD Freeman HS Cable Troubleshoot T&M T&M | Ednetics Inc | — |
| Aug 14, 2019 | Freeman SD, Freeman MS, Stairs & Vestibules / 13589 6021801000 | CHARLES H BERESFORD CO INC | $5,561 |
| Aug 8, 2019 | 19-05392 Freeman SD Camera Repairs T&M T&M | Ednetics Inc | — |
| Jul 9, 2019 | Freeman High School Tennis Courts NA | ARROW CONCRETE & ASPH SPC INC | $1,750 |
| Jul 2, 2019 | 19-05244 Freeman SD E-Rate Firewall & Wireless Access Points Letter of Intent dated 5/20/19 | Ednetics Inc | $48,035 |
| Jun 21, 2019 | 19-05299 Freeman SD DMP Panel Troubleshoot T&M T&M | Ednetics Inc | — |
| Oct 26, 2018 | 18-04468 Freeman SD Pole Vault T&M T&M | Ednetics Inc | — |
| Aug 1, 2018 | Freeman High School Tennis Courts | ARROW CONCRETE & ASPH SPC INC | $1,500 |
| Jun 25, 2018 | 18-04248 Freeman SD IP Security Upgrades 7001701005 | Ednetics Inc | $128,761 |
| Jun 7, 2018 | 2018 Freeman Middle School Roofing Project | ALL SURFACE ROOFING/WATERPRFG | $121,584 |
| May 8, 2018 | Service Shop Door 14948649 | NATIONSERVE DIV/OVRHD DR CORP | $190 |
| Apr 5, 2018 | Freeman Middle School | COBRA BEC OF SPOKANE LLC | — |
| Sep 18, 2017 | Freeman High School | BELFOR USA GROUP INC | $5,000 |
| Mar 29, 2017 | Freemen School - Steam Well Piping PO:8001601019 | K C CHARLES INC | $1,070 |
| Sep 15, 2016 | (title withheld) 7001501062, 063, 064 | EDNETICS INC | $19,714 |
| Aug 22, 2016 | 16-02421 Freeman SD - Projector Mounting T&M | EDNETICS INC | — |
| Jul 7, 2016 | Service Garage Door | OVERHEAD DOOR CORPORATION | — |
| Sep 2, 2014 | WA14-0317C Freeman SD - Security Upgrades 1001401018 | EDNETICS INC | $34,242 |
| Sep 11, 2013 | WA13-0129C Freeman SD - Polevault Install WA13-0129C | EDNETICS INC | $13,532 |
| Jul 17, 2013 | Freeman Middle School Admin. Offices 1322 | WALKER CONSTRUCTION INC | $38,689 |
| Jun 11, 2013 | (title withheld) WA13-0178C | EDNETICS INC | $34,841 |
| Apr 23, 2013 | Drilling of Well PO 6021201035 | H2O WELL SERVICE INC | $30,000 |
| Feb 12, 2013 | WA13-0039C Freeman Transportation Cabling & Intercom WA13-0039C | EDNETICS INC | $1,617 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.