EAST COLUMBIA BASIN IRRIG DISTRICT — public works contracts
124 public works projects and 160 intents to pay prevailing wages name EAST COLUMBIA BASIN IRRIG DISTRICT as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Diking/Drainage/Irrigation District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 9 | 4 | 2 | 2 | 3 | 4 | 12 | 17 | 17 | 13 |
Latest contracts (75)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Sep 17, 2026 | HMA Patching for Road Crossings 2026-02 | C & E TRENCHING LLC | $23,950 |
| Apr 13, 2026 | ECBID HMA Patching for Road Crossings - 3 2026-4 | C & E TRENCHING LLC | $33,875 |
| Mar 9, 2026 | ELC Panels 2026 0303-P | AAA Readymix, Inc. II | — |
| Jan 20, 2026 | (title withheld) Polyurea Sealant (Concrete Liner Application) 2025-01 | COLUMBIA IND COATINGS LLC | $475,200 |
| Nov 12, 2025 | HMA Patching for Road Crossing EL84.7A | QUALITY PAVING INC | $8,656 |
| Apr 21, 2025 | HMA Patching for Road Crossings - 2 69086 | ALL SERVICE ASPHALT LLC | $25,617 |
| Apr 17, 2025 | 504 S Maple Ave 120424 | ASBESTOS & MOLD SOLUTIONS INC | $31,837 |
| Mar 13, 2025 | Rd. 16 Bridge 031425-16 | AAA Readymix, Inc. II | — |
| Feb 26, 2025 | Othello Canal Polyurea Application Polyurea Sealant Application 2024-01 | COLUMBIA IND COATINGS LLC | $487,080 |
| Feb 7, 2025 | ELC Liner Replacement 2025-01 | HALME CONSTRUCTION INC | $402,600 |
| Jul 12, 2024 | East Columbia Basin Irrigation District (Pump Station) 735606 | CAMPBELL COOL ELEC PLMB CORP | — |
| Jun 19, 2024 | East Columbia Basin Irrigation District 731649 | CAMPBELL COOL ELEC PLMB CORP | — |
| May 22, 2024 | East Columbia Basin Irrigation District 725560 | CAMPBELL COOL ELEC PLMB CORP | $427 |
| May 10, 2024 | East Columbia Basin Irrigation District (Pump House) 722578 | CAMPBELL COOL ELEC PLMB CORP | $279 |
| May 9, 2024 | HVAC maintenance 2024-2025 | CAMPBELL COOL ELEC PLMB CORP | $2,975 |
| May 9, 2024 | HVAC maintenance 2024-2025 | CAMPBELL COOL ELEC PLMB CORP | $6,654 |
| May 9, 2024 | HVAC maintenance 2024-2025 | CAMPBELL COOL ELEC PLMB CORP | $3,306 |
| May 9, 2024 | HVAC maintenance 2024-2025 | CAMPBELL COOL ELEC PLMB CORP | $2,792 |
| Apr 16, 2024 | Asphalt patching P24008 | EAST SIDE ASPHALT INC | $9,196 |
| Mar 5, 2024 | Panels 2024 0304 | AAA Readymix, Inc. II | — |
| Jan 16, 2024 | Asbestos Abatement - Hampton Rd 163-01 RFQ | ASBESTOS & MOLD SOLUTIONS INC | $3,780 |
| Nov 8, 2023 | ABATEMENT � 521-02 RFQ 1 | Asbestos Central LLC | $6,423 |
| May 25, 2023 | 8th Ave Handicap Parking & Striping Project 61046 | COLUMBIA BASIN STRIPING LLC | $1,622 |
| Feb 7, 2023 | Polyurea Canal Walls 2022-01 | COLUMBIA IND COATINGS LLC | $163,402 |
| Feb 6, 2023 | District House District House | Asbestos Central LLC | $4,858 |
| Dec 12, 2022 | ECBID Adams Road 331-5615 | ALL-SAFE ABATEMENT SERVICES | $5,100 |
| Feb 22, 2022 | Concrete Liner Application Polyurea Sealant 2021-01 | REED ENVIRONMENTAL LLC | $73,844 |
| May 20, 2021 | Asphalt Patch 2021 0408 | EAST SIDE ASPHALT INC | $22,170 |
| Apr 14, 2021 | Asphalt Patch 2021 0408 | EAST SIDE ASPHALT INC | $22,170 |
| Apr 14, 2021 | Asphalt Patch 2021 0408 | EAST SIDE ASPHALT INC | $22,170 |
| Jun 16, 2020 | asphalt patching 0528 | EAST SIDE ASPHALT INC | $4,855 |
| Mar 16, 2020 | Concrete Liner Application 2020-01 | MATHESON PAINTING | $71,155 |
| Mar 4, 2019 | Concrete Liner Application 14-06-100-64190 | MATHESON PAINTING | $57,841 |
| May 24, 2018 | Asphalt Patch-Hatton RD | EAST SIDE ASPHALT INC | $5,233 |
| Mar 28, 2018 | Moses Lake Panel Replacements Moses Lake Panel Replacements | C P M DEVELOPMENT CORPORATION | — |
| Mar 20, 2018 | EAST LOW CANAL PANELS 2018 61033 | Ralph's Concrete Pumping | — |
| Feb 8, 2018 | EL47.5 PUMPING STATION EL47.5 | C P M DEVELOPMENT CORPORATION | — |
| Jun 23, 2017 | 509 Adams Street | ALL-SAFE ABATEMENT | $13,600 |
| May 9, 2017 | asphalt patch | EAST SIDE ASPHALT INC | $4,117 |
| Feb 2, 2017 | EL47.5 PUMPING STATION | Ralph's Concrete Pumping | — |
| Dec 3, 2016 | Electrical Fire | HOMESLEY CONSTRUCTION INC | $28,928 |
| Oct 24, 2016 | East Low Canal Warden Siphon | ROTSCHY INC | $1,685,825 |
| Aug 2, 2016 | 10 Car Garage | WESCO OVERHEAD DOOR CO | $8,146 |
| Jul 25, 2016 | (title withheld) | A1 ASBESTOS LLC | $2,134 |
| Apr 6, 2016 | EAST LOW CANAL PANEL REPLACEMENT 2016 | Ralph's Concrete Pumping | — |
| Feb 19, 2016 | Calloway Road Bridge Shotcrete Placement | COLUMBIA PUMPING & CONST INC | $79,025 |
| Jan 28, 2016 | CALLOWAY ROAD BRIDGE PROJECT | Ralph's Concrete Pumping | — |
| Nov 24, 2015 | Calloway Bridge Rock Dowel Installation | BUDINGER & ASSOCIATES INC | $42,940 |
| Aug 3, 2015 | Garage Doors None | WESCO OVERHEAD DOOR CO | $9,252 |
| May 27, 2015 | LEISLE ROAD BRIDGE 410-3 | CENTRAL WASHINGTON ASPHALT INC | $33,795 |
| May 14, 2015 | (title withheld) 410-3 | PETERSEN BROTHERS INC | $65,981 |
| May 11, 2015 | County Road Restoration | EAST SIDE ASPHALT INC | $13,128 |
| Apr 2, 2015 | East Low Canal Panel Replacement 2015 | Ralph's Concrete Pumping | — |
| Mar 18, 2015 | LEISLE ROAD BRIDGE 01 | Pat's Portable Welding | — |
| Mar 12, 2015 | East Low Canal Lind Coulee #1 & #2 Siphons | ROTSCHY INC | $13,580,797 |
| Mar 10, 2015 | Calloway Road Bridge #412-3 & Leisle Road Bridge #410-3 | AAA Readymix, Inc. II | — |
| Feb 24, 2015 | Leisle Road Bridge #410-3 | CONCRETE TECHNOLOGY CORP | $289,372 |
| Feb 16, 2015 | EAST LOW CANAL OB3 LINING REPAIR | Ralph's Concrete Pumping | — |
| Jan 14, 2015 | Leisle rd bridge and Calloway rd Bridge not applicable | Morse Steel Service | $117,896 |
| Jan 12, 2015 | Six Pump Stations Buildings 5 | CULBERT CONSTRUCTION INC | $79,300 |
| Dec 12, 2014 | LCWW AND LC1 RADIAL GATE FABRICATINO LCWW | FABRICATION PRODUCTS INC | $160,512 |
| Aug 19, 2014 | Garage Doors | WESCO OVERHEAD DOOR CO | $12,379 |
| Jul 29, 2014 | asphalt patch om Road K SE | EAST SIDE ASPHALT INC | $2,284 |
| Jul 23, 2014 | MOSES LAKE WATERMASTER BUILDING Q000869 | AL'S GLASS SERVICE INC | $5,023 |
| May 20, 2014 | ROAD P SE | CENTRAL WASHINGTON ASPHALT INC | $4,760 |
| Jan 7, 2014 | Installation of Conservation Pipelines | PREMIER EXCAVATION INC | $473,654 |
| Nov 25, 2013 | 2013 Pump Houses | VALLEY MASONRY & CONST LLC | $75,500 |
| May 28, 2013 | Road 5.6 NE Patch | EAST SIDE ASPHALT INC | $4,856 |
| May 2, 2013 | Lind Coulee Waste Way Branch | TAPANI INC | $22,728 |
| Dec 7, 2012 | ECBID Installation of Conservation Pipelines N/A | APOLLO INC | $1,455,922 |
| Nov 29, 2012 | East Low Canal Widening Project | TAPANI INC | $863,926 |
| Nov 21, 2012 | SB & Coat 3 Large Canal Radial Gates None | E C I SERVICES | $34,218 |
| Oct 28, 2012 | 2012 Pump Houses | VALLEY MASONRY & CONST LLC | $79,489 |
| Feb 6, 2012 | 2012 Concrete Liner Application 9039 | MATHESON PAINTING | $104,444 |
| Oct 31, 2011 | 2011 Pump Houses | VALLEY MASONRY & CONST LLC | $90,480 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.