23 public works projects and 31 intents to pay prevailing wages name COLUMBIA CONSERVATION DISTRICT as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Conservation District.

Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.

Intents filed, by year

2015201620172018201920202021202220232025
5122221233

Latest contracts (23)

Intent filedContractPrime contractorAmount declared
Jun 5, 2025Tucannon River Habitat Restoration , Project 34.1 & 34.2
NA
ROYSE HYDROSEEDING$898,386
Sep 8, 2023Tucannon Project Areas 26 Phase 2 2023 Maintenance
NA
ROYSE HYDROSEEDING$26,000
Feb 28, 2023Tucannon River Habitat Restoration, Project Area 26 Phase III & IV Construction & Materials
2022-02
F & R CONSTRUCTION$747,451
Oct 7, 2022Tucannon River Habitat Restoration, PA 26 Phase III & IV Pivot Materials & Construction
PA 26: 2022-01
DIS NORTHWEST INC$148,085
Jul 29, 2021Tucannon River Habitat Restoration, Project Area 26
2021-02
ROYSE HYDROSEEDING$238,933
Aug 4, 2020Tucannon Project Areas 24 Maintenance 2020 Construction
2020-02
ROYSE HYDROSEEDING$78,553
Aug 4, 2020Tucannon River Habitat Restoration, Project Area 28 Maintenance 20202
2020-03
ROYSE HYDROSEEDING$30,512
Sep 2, 2019Tucannon Project Areas 28 2019 Maintenance
NA
ROYSE HYDROSEEDING$7,475
Sep 2, 2019Tucannon Project Areas 32 Habitat Construction
NA
ROYSE HYDROSEEDING$231,873
Aug 2, 2018TUCANNON PROGECT AREA 40
PA24&26
F & R CONSTRUCTION$27,137
Jun 25, 2018Tucannon River 2018 habitat project
2018-03
ECOGRIND SITE SOLUTIONS LLC$154,936
Jul 24, 2017PA 24 Maintenance Project
2017-03
ROYSE HYDROSEEDING$45,579
Apr 26, 2017Project Area 28 Phase II Habitat Construction
RFB 2017-02 PA-28
BARKER INC$224,632
Jun 15, 2016Tucannon Project Areas 28 Habitat Construction
NA
ROYSE HYDROSEEDING$187,827
Jul 22, 2015tucannon Project Area 23 Habitat Construction
23
ECOGRIND SITE SOLUTIONS LLC$83,778
Jul 22, 2015Tucannon Project Area 26 Habitat Construction
26
ECOGRIND SITE SOLUTIONS LLC$25,944
Jul 13, 2015Tucannon Project Area 24 Habitat Construction
NA
ROYSE HYDROSEEDING$338,512
Jun 22, 2015TUCANNON RIVER 2015 HABITAT
PA 23, PA24
F & R CONSTRUCTION$151,000
Sep 30, 2014TUCANNON PROJECT AREA 40
PA 40
F & R CONSTRUCTION$180,527
Jul 31, 2014Tucannon River Project Area 15
2014-001-15
JANSEN INC$337,643
Jul 15, 2014Tucannon Project Areas 15 Access Road Construction
PA 15
BARKER INC$76,756
Jul 15, 2014Tucannon Project Areas 22 & 26 Habitat Construction
PA 22 PA26
BARKER INC$39,456
Aug 20, 2013(title withheld)
TUCWS1301
BARKER INC$189,980

Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.

Contractors that filed intents on its projects

ContractorIntents on this agency's projects
BARKER INC4
Cat's Center Pivot Inc1
CENTRAL WASHINGTON ASPHALT INC1
ECOGRIND SITE SOLUTIONS LLC3
F & R CONSTRUCTION4
HDJ Design Group, PLLC1
JANSEN INC1
KING CONSTRUCTION SRVCS WA LLC1
METALCRAFT NORTHWEST INC1
ROCK HILL CONCRETE LLC1
RON DUNNING FARMS INC1
Ronald T. Jepson & Associates2
ROYSE HYDROSEEDING10