43 public works projects and 54 intents to pay prevailing wages name Columbia Basin Hydropower as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Public Utility District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2016 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 5 | 1 | 5 | 11 | 4 | 1 | 4 | 3 | 3 | 5 |
Latest contracts (39)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Sep 11, 2026 | Main Canal 5-31-24 | DELTA STAR INC | $2,034,873 |
| Sep 11, 2026 | Summer Falls Power Project 6-16-24 | DELTA STAR INC | $2,605,958 |
| May 8, 2026 | 294864 - SUMMER FALLS POWER PLANT MOD 294864 | TK ELEVATOR CORPORATION | $264,419 |
| Feb 23, 2026 | Summer Falls Plant 111111 | K&W GLASS & AUTOMOTIVE RPR LLC | $8,652 |
| Jan 27, 2026 | Oil Storage Tank Formed Parts 7-2025-1006 | Waite Specialty Machine Works, Inc | $29,154 |
| Nov 3, 2025 | Summer Falls Power Plant 7-2022-1004 | FIRE PROTECTION SPEC LLC | $56,374 |
| Nov 3, 2025 | MC Shop Bridge Crane Removal and Replacement Q004793 | WASHINGTON CRANE & HOIST LLC | $258,650 |
| Jan 4, 2025 | SF U162 Draft Tube Drain Restriction Removal 6-18-25 | CLEAR STONE GEO LLC | $27,000 |
| Apr 22, 2024 | (15) Annual NFPA10 Extinguisher Inspection(s) 12585260 | Performance Systems Intgn LLC | $258 |
| Apr 22, 2024 | (24) Annual NFPA10 Extinguisher Inspection(s 12585247 | Performance Systems Intgn LLC | $519 |
| Apr 22, 2024 | (32) Annual NFPA10 Extinguisher Inspection 12585250 | Performance Systems Intgn LLC | $435 |
| Mar 29, 2023 | Columbia Basin Hydropower - FE Inspections 12356-24-23 | Performance Systems Intgn LLC | $1,075 |
| Feb 8, 2023 | Main Canal Concrete Liner Repair 6-14-23 | HALME CONSTRUCTION INC | $59,510 |
| Oct 25, 2022 | CBHP (Summer Falls Pole Replacement) N/A | POTELCO INC | $280,999 |
| Dec 28, 2021 | Design and equip for fire detection system 7-2021-1001 | FIRE PROTECTION SPEC LLC | $33,458 |
| Oct 27, 2021 | Summer Falls 6-9-21 | Hungry Horse Panels | $293,812 |
| Oct 1, 2021 | CrackSeal Project Powerplant | QUALITY PAVING INC | $42,364 |
| Mar 30, 2021 | PEC 66 Trash Rake Upgrade PEC-66-2020 | PASCO MACHINE COMPANY INC | $33,253 |
| Nov 24, 2020 | Snow Removal snow123 | DIRCIO'S LANDSCAPING LLC | $150 |
| Nov 19, 2020 | Sign Foundation 2204 | DIRCIO'S LANDSCAPING LLC | $2,385 |
| Nov 14, 2020 | summer falls power plant maint | THYSSENKRUPP ELEVATOR CORP | $1,352 |
| Aug 18, 2020 | Main Canal Panels 5-27-20 | Hungry Horse Panels | $129,670 |
| Jun 10, 2020 | SUMMER FALLS POWER PLNT Maint 06-01-20 to 08-31-20 | THYSSENKRUPP ELEVATOR CORP | $1,400 |
| Jun 10, 2020 | SUMMER FALLS POWER PLNT Maint 03-01-20 to 05-31-20 | THYSSENKRUPP ELEVATOR CORP | $1,396 |
| May 27, 2020 | Landscape Maintenance 1018 | DIRCIO'S LANDSCAPING LLC | $2,385 |
| Apr 30, 2020 | SUMMER FALLS POWER PLNT signed proposal | THYSSENKRUPP ELEVATOR CORP | $5,282 |
| Mar 12, 2020 | (title withheld) PEC66-04052019 | ALL-SAFE ABATEMENT SERVICES | $1,167 |
| Mar 12, 2020 | PCM Air Monitoring PEC66-04052019 | ALL-SAFE ABATEMENT SERVICES | $850 |
| Feb 7, 2020 | Summer Falls Power Plant signed work order | THYSSENKRUPP ELEVATOR CORP | $4,895 |
| Sep 30, 2019 | 46,66 Panel Fabrication 23-17-19 | Hungry Horse Panels | $109,000 |
| Sep 22, 2019 | Install Chain Link Fence Gates 12829 | NORTH CENTRAL WASH FENCE LLC | $6,330 |
| Jul 30, 2019 | Russell D Smith Power Plant Governor/Hydralic System Upgrade 01-11-19 | AMERICAN GOVERNOR COMPANY | $274,469 |
| Nov 8, 2018 | Main Canal Power Plant Steel Storage Building 05-26-18 | HALME BUILDERS INC | $215,800 |
| Nov 4, 2016 | Main Canal Power Plant 5-2016-1033 | NORTH AMERICAN SBSTTN SVCS LLC | $37,495 |
| Oct 24, 2016 | Main Canal Power Plant Rehabilitation of Intake Gates 05-25-2016 | J R MERIT INC | $1,372,047 |
| Nov 10, 2015 | Potholes East Canal Mile 22.7 Check Structures 01-10-15 | MOUNTAIN STATES CONST CO | $225,000 |
| Jan 5, 2015 | Exciter and Governor Replacement Prj 56-04-13 | EATON CORPORATION | $2,559,302 |
| Dec 3, 2012 | Summer Falls Culvert Repair 2012-12 | ROCK STEEL STRUCTURES INC | $5,875 |
| Aug 5, 2011 | GCPHA Main Canal Power Plant 1153 | SIMPLEXGRINNELL LP | $2,734 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.