CASCADE MEDICAL CENTER — public works contracts
148 public works projects and 185 intents to pay prevailing wages name CASCADE MEDICAL CENTER as the awarding agency, in the L&I file of Oct 1, 2026. L&I classes it as: Health District.
Bidding, hiring a subcontractor or checking a competitor? A dated public works report ($19) on one contractor — or an agency's awards, every month.
Intents filed, by year
| 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|---|---|
| 3 | 5 | 18 | 15 | 17 | 22 | 26 | 2 | 7 | 1 |
Latest contracts (112)
| Intent filed | Contract | Prime contractor | Amount declared |
|---|---|---|---|
| Feb 27, 2026 | (title withheld) 525439 | KEYHOLE SECURITY INC | $11,886 |
| Aug 26, 2025 | Cascade Medical Center, Laundry Room Drain Chad | AFTER HOURS PLUMBING & HTG INC | $1,048 |
| Aug 21, 2025 | CMC Clinic Nurse Area Renovation c-cwp-2025 | JESSUP HOME DESIGN INC | $122,706 |
| Jun 11, 2025 | VAV 2-16 NO HEAT N/C | SALCIDO CONNECTION INC, THE | — |
| Apr 1, 2025 | INSTALL OPERATOR 03242025 | DOOR-TECH INC | $4,162 |
| Jan 4, 2025 | Fire Inspection 1026629 | KEYHOLE SECURITY INC | — |
| Jan 12, 2024 | Fire Inspection 1022491 | KEYHOLE SECURITY INC | — |
| Dec 28, 2023 | MRI Trailer Plan Review & Power Monitoring N/A | SALCIDO CONNECTION INC, THE | $12,371 |
| Dec 28, 2023 | Cascade Medical - Leavenworth DIV9-5964 | DIVISION 9 INC | $88,000 |
| Dec 27, 2023 | Therapy Pool HVAC System Additions & Alterations N/A | SALCIDO CONNECTION INC, THE | $65,084 |
| Dec 27, 2023 | Ductless Mini-Split System Installations N/A | SALCIDO CONNECTION INC, THE | $69,614 |
| Dec 19, 2023 | Mechanical Commissioning & Reporting N/C | SALCIDO CONNECTION INC, THE | $57,174 |
| Oct 16, 2023 | Heat tape electrical work Heat tape electrical work | Pine to Sage Electric LLC | $2,490 |
| Oct 11, 2023 | Cascade Medical Building 5096686732 | CW PAINTING LLC | $69,961 |
| Jun 23, 2023 | Emergency Department Chad | AFTER HOURS PLUMBING & HTG INC | $915 |
| Jun 23, 2023 | Emergency Department Sink Chad | AFTER HOURS PLUMBING & HTG INC | $1,326 |
| Jun 23, 2023 | PT Shower Valve Replacements Chad | AFTER HOURS PLUMBING & HTG INC | $1,820 |
| Jun 23, 2023 | Pediatric Rehab Room Chad | AFTER HOURS PLUMBING & HTG INC | $2,030 |
| May 25, 2023 | 200 Ton Chiller Replacement N/A | SALCIDO CONNECTION INC, THE | $368,211 |
| May 18, 2023 | Repair or Replace wireless door lock 5923 | KEYHOLE SECURITY INC | — |
| May 17, 2023 | Upgrade Device Change N/A | SALCIDO CONNECTION INC, THE | $2,045 |
| May 17, 2023 | Additional Approved Chiller Repairs N/A | SALCIDO CONNECTION INC, THE | — |
| May 5, 2023 | 190 Ton Chiller Diagnostic & Repairs N/A | SALCIDO CONNECTION INC, THE | — |
| Apr 12, 2023 | Hallway Lift Charger Outlet Installation N/A | SALCIDO CONNECTION INC, THE | $1,248 |
| Mar 22, 2023 | Main AHU Return Issues N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 22, 2023 | Glycol Feeder Pump Tripping GFCI N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 22, 2023 | 20 Ton RTU Chiller CU Fan Replacements N/A | SALCIDO CONNECTION INC, THE | $3,738 |
| Mar 14, 2023 | 20 Ton RTU Chiller Compressor Replacement N/A | SALCIDO CONNECTION INC, THE | $10,139 |
| Mar 14, 2023 | Main HVAC Actuator & Air Balancing N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 14, 2023 | Ambulance Garage - Replace Faulty Outlet N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 8, 2023 | Station 93 medical van power 1000-2466 | FIRST CHOICE ELECTRIC LLC | — |
| Mar 7, 2023 | OPERATOR & KEYPADS FOR CASCADE MEDICAL CENTER 02032023 | DOOR-TECH INC | $3,765 |
| Jan 12, 2023 | Annual fire system inspection 12272022 | KEYHOLE SECURITY INC | — |
| Dec 29, 2022 | Clinic Entry Doors Not Working Properly N/A | SALCIDO CONNECTION INC, THE | — |
| Dec 29, 2022 | Server Room - Replace 8 Outlets N/A | SALCIDO CONNECTION INC, THE | — |
| Dec 6, 2022 | Ambulance Garage - Replace Electric Heater N/A | SALCIDO CONNECTION INC, THE | — |
| Oct 11, 2022 | Lab Area Ductless Split System Installation N/A | SALCIDO CONNECTION INC, THE | $12,233 |
| Oct 11, 2022 | Install new kitchen equipment circuit N/A | SALCIDO CONNECTION INC, THE | — |
| Sep 9, 2022 | Install power door operator 8242022 | KEYHOLE SECURITY INC | $9,496 |
| Aug 12, 2022 | Cat6 Cable Pulls N/A | SALCIDO CONNECTION INC, THE | $1,015 |
| May 25, 2022 | Boiler Pressure Relief Valve Replacement N/A | SALCIDO CONNECTION INC, THE | — |
| May 12, 2022 | Kitchen Electrical Evaluation N/A | SALCIDO CONNECTION INC, THE | — |
| Apr 28, 2022 | Mechanical Room Breaker Tripping N/A | SALCIDO CONNECTION INC, THE | — |
| Apr 13, 2022 | Ambulance Bay Glycol Boiler Down N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 24, 2022 | Install cameras in pharmacy 31622 | KEYHOLE SECURITY INC | $7,387 |
| Feb 16, 2022 | Lab/Misc. Room - Add Electrical Circuit N/A | SALCIDO CONNECTION INC, THE | — |
| Feb 10, 2022 | Annual Fire Inspection 2102022 | KEYHOLE SECURITY INC | — |
| Jan 20, 2022 | Basement Storage Rm LED Lights N/A | SALCIDO CONNECTION INC, THE | — |
| Jan 20, 2022 | AHU-1 Replace Burnt LS N/A | SALCIDO CONNECTION INC, THE | — |
| Oct 4, 2021 | Circuit Extension & Repair N/A | SALCIDO CONNECTION INC, THE | — |
| Oct 4, 2021 | (title withheld) N/A | SALCIDO CONNECTION INC, THE | — |
| Jun 29, 2021 | Admin Building Not Cooling N/A | SALCIDO CONNECTION INC, THE | — |
| Jun 29, 2021 | Chiller Leaking & Won't Start N/A | SALCIDO CONNECTION INC, THE | — |
| Jun 23, 2021 | Admin Bldg. No AC Cooling N/A | SALCIDO CONNECTION INC, THE | — |
| Jun 9, 2021 | Trailer Shore Power Circuit N/A | SALCIDO CONNECTION INC, THE | $3,271 |
| Jun 9, 2021 | Central Supply Light Addition N/A | SALCIDO CONNECTION INC, THE | $374 |
| Jun 9, 2021 | Main Level Restroom Door Circuit N/A | SALCIDO CONNECTION INC, THE | $4,828 |
| May 20, 2021 | Upgrade Access System 05202021 | KEYHOLE SECURITY INC | $61,259 |
| May 3, 2021 | Unit#2 - Large Air Handler Not Cooling Properly N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 17, 2021 | Install Central Supply Data Drop N/A | SALCIDO CONNECTION INC, THE | $770 |
| Mar 10, 2021 | Install Video Intercom 03102021 | KEYHOLE SECURITY INC | $10,747 |
| Feb 8, 2021 | Install Monitoring Cable 02082021 | KEYHOLE SECURITY INC | — |
| Jan 27, 2021 | Elevator Control Room Light Installation N/A | SALCIDO CONNECTION INC, THE | — |
| Jan 8, 2021 | Install Printer Data Drops N/A | SALCIDO CONNECTION INC, THE | — |
| Jan 8, 2021 | Elevator Breaker Replacement N/A | SALCIDO CONNECTION INC, THE | — |
| Dec 7, 2020 | Duct Heater #6 Controller Replacement N/A | SALCIDO CONNECTION INC, THE | $716 |
| Dec 4, 2020 | Duct Heater Disconnect Replacement N/A | SALCIDO CONNECTION INC, THE | — |
| Oct 28, 2020 | CT Scanner Breaker Replacement N/A | SALCIDO CONNECTION INC, THE | — |
| Oct 13, 2020 | CAT Scan Room Outlet Repair N/A | SALCIDO CONNECTION INC, THE | — |
| Oct 13, 2020 | Emergency Room Light Repair N/A | SALCIDO CONNECTION INC, THE | — |
| Aug 28, 2020 | DW Booster Heater Circuit Upgrade N/A | SALCIDO CONNECTION INC, THE | — |
| Jul 3, 2020 | (title withheld) 7032020 | KEYHOLE SECURITY INC | $4,371 |
| Apr 9, 2020 | Access System Additions 4012020 | KEYHOLE SECURITY INC | $23,426 |
| Feb 21, 2020 | Cascade Medical Center Clinic Shelled Infill 111-17104 | WHITEBIRD INCORPORATED | $104,479 |
| Dec 18, 2019 | Upgrade Access System software 12182019 | KEYHOLE SECURITY INC | $3,425 |
| Nov 12, 2019 | Add new magnetic door holder 11122019 | KEYHOLE SECURITY INC | $1,812 |
| Oct 2, 2019 | Cascade Medical PT Water Damage PT Water Damage | FRANCE & CO | $20,000 |
| Sep 18, 2019 | Chemical Analyzer Circuit N/A | SALCIDO CONNECTION INC, THE | — |
| May 23, 2019 | New Parking Facility None | KRCI LLC | $302,436 |
| May 9, 2019 | Access at Clinic lobby door 515384 | KEYHOLE SECURITY INC | $3,425 |
| Mar 26, 2019 | Rehab Services - LED Lights Out N/A | SALCIDO CONNECTION INC, THE | — |
| Mar 11, 2019 | Power Door Operator 197631 | KEYHOLE SECURITY INC | $6,887 |
| Jan 28, 2019 | Exterior Ambulance Outlet Installion N/A | The Salcido Connection, Inc. | $1,897 |
| Jan 28, 2019 | ED Nurse's Station Data Installation N/A | The Salcido Connection, Inc. | $1,642 |
| Jan 24, 2019 | Family Clinic Reception Power Data N/A | The Salcido Connection, Inc. | $1,783 |
| Jan 24, 2019 | AHU-2 Motor Replacement N/A | The Salcido Connection, Inc. | $2,076 |
| Dec 28, 2018 | Annual Fire Alarm Inspection n/a | KEYHOLE SECURITY INC | $1,041 |
| Nov 8, 2018 | AHU-2 Duct Heater Issues NA | SALCIDO CONNECTION INC, THE | — |
| Sep 20, 2018 | Ambulance Parking Bay HVAC Installation NA | SALCIDO CONNECTION INC, THE | $12,905 |
| Mar 23, 2018 | (3) Circuit Extensions NA | SALCIDO CONNECTION INC, THE | $2,943 |
| Jan 17, 2018 | Power Door Operators n/a | KEYHOLE SECURITY INC | $9,456 |
| Aug 3, 2017 | ASPHALT MAINT. 2017-004 | BLACKROCK ASPH & CONC CTGS INC | $9,000 |
| Jun 5, 2017 | Clinic Wall Removal & Electrical/Data Outlet Relocation N/A | SALCIDO CONNECTION INC, THE | $5,051 |
| Feb 3, 2017 | POD#4 Data - ER Monitor Outlet & Data Drop | SALCIDO CONNECTION INC, THE | $4,098 |
| Oct 3, 2016 | Duct Cleaning | CLEAN AIR CONNECT/CLEAN CONN | $33,515 |
| Aug 19, 2016 | Cascade Medical Center | MITCHELL TRUCKING & PAVING INC | $12,027 |
| May 3, 2016 | Power Door Ops & New Cameras 197140 & 197141 | KEYHOLE SECURITY INC | $12,681 |
| Jul 17, 2015 | Add access in ER 196950 | KEYHOLE SECURITY INC | $5,483 |
| Feb 11, 2015 | Add Mag Holds to Fie System n/a | KEYHOLE SECURITY INC | $2,687 |
| Dec 16, 2014 | Cascade Medical Center W14-492P | INLAND FIRE PROTECTION INC | $1,371 |
| Jul 8, 2014 | Dishwasher Dishwasher | PATRIOT PLBG/HTG & COOLING INC | — |
| Jun 11, 2014 | Install Front Lobby Camera n/a | KEYHOLE SECURITY INC | $1,352 |
| Jan 14, 2014 | Basement Repipe 2014-001 | PATRIOT PLBG/HTG & COOLING INC | $27,550 |
| Dec 24, 2013 | Annual Fire Inspection N/A | KEYHOLE SECURITY INC | — |
| Apr 9, 2013 | Physical Therapy Work Station Addition | WESTERN STATES CONSTR INC | — |
| Jan 29, 2013 | Fire System Inspection N/A | KEYHOLE SECURITY INC | $992 |
| Jan 15, 2013 | paver modifications 12/1 | ROSALES LANDSCAPING INC | $2,905 |
| Jan 13, 2013 | Cascade Medical Center Clinic Build-Out | WESTERN STATES CONSTR INC | $212,268 |
| Jul 24, 2012 | Financial Councilor's Office 2011.01 | HILDEBRAND CONSTRUCTION INC | $10,466 |
| Feb 7, 2012 | Cascade Medical Center Attic Roofing 14196 | I R S ENVIRONMENTAL OF WA INC | $30,081 |
| Nov 1, 2011 | INSTALL TRACK LIGHTING IN CHAPEL 12742 | APPLE CITY ELECTRIC LLC | — |
| Jun 29, 2010 | Cascade medical center addition and modernization | RAVEN GLASS & MIRROR | $100,950 |
Most recent first. Each amount is the figure declared on the prime contractor's intent; amounts are not added up. Project addresses are not published.
Contractors that filed intents on its projects
Alphabetical order; the 25 contractors with the most filings on this agency's projects, prime and subcontractors together.